Inspections for the day of: Thursday, April 23, 2020.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC19-01706 General Inspection4/23/20204/23/20204/24/2020 9:56:36 AMPPASS
Sidewalks LLc on side doing curbing, knife river delivering mud. Did not see a washout or any dumped washout on site. No construction entrance, area is prepped for road bed.
Sidewalk and curbing on Boise ASve also needs to be installed.
ESC06-01306 Site Final4/23/20204/23/20204/24/2020 9:21:35 AMPPASS
Exterior construction and landscaping completed. Site is clean, no issues.
ESC19-00859 Aging Inspection4/23/20204/23/20204/23/2020 2:53:10 PM CANC
ESC19-00859 DOC - Permit Finaled4/23/20204/23/20204/23/2020 2:53:00 PMPPASS
ESC19-00836 DOC - Permit Finaled4/23/20204/23/20204/23/2020 2:52:25 PMPPASS
Looks completed, no disturbed area. No recent BLD activity.
ESC19-00927 General Inspection4/23/20204/23/20204/23/2020 2:42:21 PMPPASS
Post rain inspection.
Hillside shows no damage or rilling. No issues at site, no runoff from bottom.
ESC19-00895 General Inspection4/23/20204/23/20204/23/2020 2:36:42 PM PASS
ESC17-00985 General Inspection4/23/20204/23/20204/23/2020 1:17:58 PM PASS
Site is contained, hillside stable.
ESC19-00324 General Inspection4/23/20204/23/20204/23/2020 12:11:43 PMPFAIL
RP on site
Utility work along warm springs. Lots of tracking across street from Boven. Silt fence will need to be repaired along warm springs.
Upper section is clean. No rills or discharged. Hillside have some growth and held up well.
ESC19-00371 General Inspection4/23/20204/23/20204/23/2020 11:49:04 AMPFAIL
Curbing and sidewalks done on first phase of upper section, road bed installed and not paved. Grass is growing very well.
Ridgepoint is closed, crew on site.
Met with Mark, Dave, and Steve on site. Part of bypass pipe may be blocked or broken. Water is coming out of sewer top, running into creek, and into new line being installed. Water is ending up behind dam instead of around it. L2 is doing minimal work today since it is to wet. They want to have sewer connection done within 7 days.
Took turbidity readings:
Pond on Vortex 308 NTU
Bypass below dam 481 NTU
Creek outflow at bottom of site: 373 NTU.
Creek between overflow and dam, all stays on site :658 NTU
Everyone was notified of issue, working on solutions.
ESC19-00260 General Inspection4/23/20204/23/20204/23/2020 11:39:53 AM PASS
Landscapers on site, some materials stored on road. No runoff or trash in drainage channel.
ESC19-01494 Tracking Control4/23/20204/23/20204/23/2020 9:44:10 AMPFAIL
Message sent to RP.
Workers parked on muddy driveway. Some trackout.