ESC17-00954
| General Inspection | 4/30/2019 | 4/30/2019 | 5/3/2019 11:19:59 AM | P | PASS |
|
|
No major issues at site, has been dry. Hillside vegetation growing in. Home with roofs still don't have gutters and may have concentrated flow when it rains. Gravel snake bags ran over and falling apart. Some loose trash blown from house on left into vacant lot.
|
ESC18-00804
| General Inspection | 4/30/2019 | 4/30/2019 | 5/1/2019 1:00:26 PM | | PASS |
|
|
Metal building is up. Construction entrance in place. Will need to watch for mud when rains.
|
ESC18-00830
| Aging Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 2:14:55 PM | | CANC |
|
|
|
ESC18-00830
| DOC - Permit Finaled | 4/30/2019 | 4/30/2019 | 4/30/2019 2:14:48 PM | P | PASS |
|
|
|
ESC18-00513
| Aging Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 2:09:52 PM | | PASS |
|
|
Multiple permits still open. No disturbances seen from front gate.
|
ESC18-00833
| Aging Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 2:07:24 PM | | CANC |
|
|
|
ESC18-00833
| DOC - Permit Finaled | 4/30/2019 | 4/30/2019 | 4/30/2019 2:07:18 PM | P | PASS |
|
|
|
ESC17-01323
| Site Final | 4/29/2019 | 4/30/2019 | 4/30/2019 2:05:31 PM | P | PASS |
|
|
|
ESC18-00818
| General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 12:46:58 PM | | PASS |
|
|
No workers on site. All building material on lot, trash box on lolt. No trackout or dirt on sidewalk.
|
ESC18-00618
| General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 12:03:09 PM | | CANC |
|
|
|
ESC18-00618
| DOC - Permit Finaled | 4/30/2019 | 4/30/2019 | 4/30/2019 12:03:02 PM | P | PASS |
|
|
|
ESC18-01289
| General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 11:57:48 AM | P | PASS |
|
|
Shotcrete wall completed, perimeter wall for first building completed. Getting ready to start with floors, will bring back eco pans. Roads are clean, not much activity.
|
ESC18-00983
| General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 11:29:41 AM | P | PART |
|
|
Some trackout onto Holcomb, lots of dust when cars run it over. Entrance is compacted and corner cut. Lots of dust when trucks pull into entrance. RP notified and follow up scheduled.
|
ESC19-00421
| General Inspection | 4/22/2019 | 4/30/2019 | 4/30/2019 10:03:06 AM | P | PASS |
|
|
Last section of greenbelt on hold due to high water. Area excavated is about even with creek elevation and full of water. Met with GC Rusty, is moving equipment of site, not expecting rivers to drop for at least 6 weeks.
|
ESC18-01597
| General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 9:42:03 AM | P | PASS |
|
|
WIP on framing. Concrete washout damaged when backfill removed, will need to be rebuilt or repaired. Site is clean, no ESC issues.
|
ESC18-00558
| General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 9:36:58 AM | | PASS |
|
|
Home is completed and lot landscaped. Multiple perits still opened.
|