ESC17-01669
| Aging Inspection | 5/15/2019 | 5/15/2019 | 5/16/2019 11:17:35 AM | | PASS |
|
|
Home completed, still needs landscaping.
|
ESC17-01670
| Aging Inspection | 5/15/2019 | 5/15/2019 | 5/16/2019 11:13:47 AM | | PASS |
|
|
Home completed, still needs landscaping.
|
ESC19-00091
| General Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 2:19:35 PM | P | PASS |
|
|
Silt fence and wattle installed, hillside also has tracking. One rill from sprinklers, water running into sewer trench. No dirt leaving site, no issues.
|
ESC18-01576
| General Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 2:18:44 PM | P | PASS |
|
|
Met with project manager. Natural buffer maintained and wattles installed. No hillside runoff. Site is clean, no ESC issues.
|
ESC18-00109
| General Inspection | 5/13/2019 | 5/15/2019 | 5/15/2019 11:50:50 AM | A | PART |
|
|
Majority cleaned, still some gravel at curb.
|
ESC19-00260
| Site Preparation | 5/13/2019 | 5/15/2019 | 5/15/2019 11:25:15 AM | A | PASS |
|
|
Met with excavator on site. Wattles have been trenched and added at bottom of lot by drainage. Rock for entrance was getting delivered. Corners of home were marked, will add silt fence along rear perimeter.
|
ESC18-00558
| General Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 11:23:38 AM | | CANC |
|
|
|
ESC18-00558
| DOC - Permit Finaled | 5/15/2019 | 5/15/2019 | 5/15/2019 11:23:33 AM | P | PASS |
|
|
|
ESC17-01656
| Aging Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 11:09:18 AM | | CANC |
|
|
|
ESC17-01656
| DOC - Permit Finaled | 5/15/2019 | 5/15/2019 | 5/15/2019 11:08:15 AM | P | PASS |
|
|
Landscaped and stable.
|
ESC18-00025
| Aging Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 10:48:27 AM | | CANC |
|
|
|
ESC18-00025
| DOC - Permit Finaled | 5/15/2019 | 5/15/2019 | 5/15/2019 10:48:22 AM | P | PASS |
|
|
|
ESC18-00172
| Aging Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 10:39:57 AM | | PASS |
|
|
Home and walls/planters completed. Still large pile of fill on site and needs stabalization. No workers on site.
|
ESC19-00299
| General Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 10:33:55 AM | P | PASS |
|
|
WIP on framing. Area is clean, no trash or ESC issues.
|
ESC19-00351
| General Inspection | 5/3/2019 | 5/15/2019 | 5/15/2019 10:08:10 AM | P | PASS |
|
|
Grading and prep for road bed completed. SIte will need new entrance when work resumes. Inlet protection installed and clean, no dirt or dust leaving site.
|
ESC18-00893
| BMP Violation | 5/3/2019 | 5/15/2019 | 5/14/2019 11:01:00 AM | A | PASS |
|
|
Stucco crew finished. Parking area cleaned and being prepped for paving. Majority of trash picked up.
|