Inspections for the day of: Thursday, May 23, 2019.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01009 General Inspection5/23/20195/23/20195/24/2019 12:14:17 PM PASS
Framing has begun. Material stored by Suez pump house, no ESC issues. Owners live next door.
ESC18-00268 DOC - Permit Finaled5/23/20195/23/20195/23/2019 12:43:34 PMPPASS
Expired.
ESC19-00371 General Inspection5/23/20195/23/20195/23/2019 12:25:20 PMPPEND
Met with Syman crew on site. SOme areas of wire back silt fence have been undercut and need repair. End of road cut in acting as channel, asked for a few tiers of wattle going down hill and also below silt fence in case of failure.
They need to get more materials and will be back. Asked to have done before rain event anticipated 5-24.
ESC17-01414 General Inspection5/23/20195/23/20195/23/2019 11:51:03 AM PART
Some mud and trash on Brookridge.
Plywood being used to keep forklift from tearing up grass. Most of site clean, mess looks to be from drywaller not cleaning after unloading material.
ESC17-00774 General Inspection5/23/20195/23/20195/23/2019 11:33:31 AM PART
Creek needs trash picked up and debris blocking flow .
ESC17-01491 General Inspection5/23/20195/23/20195/23/2019 10:55:25 AM PASS
Creek is flowing clean. No rills or runoff going to creek.
ESC18-00723 Aging Inspection5/23/20195/23/20195/23/2019 10:21:01 AM CANC
ESC18-00747 Aging Inspection5/23/20195/23/20195/23/2019 10:20:46 AM CANC
ESC18-00723 DOC - Permit Finaled5/23/20195/23/20195/23/2019 10:20:38 AMPPASS
ESC18-00747 DOC - Permit Finaled5/23/20195/23/20195/23/2019 10:20:28 AMPPASS
ESC18-00179 BMP Violation5/21/20195/23/20195/22/2019 3:20:04 PMAPASS
Met with Joey on site. Has crew sweeping roads, sidewalks, and alleys, done at end of day. New RP will be taking over as he transitions to office.
Split rail fence to be installed with silt fence along it acting as wind fence to prevent blown trash. North side of park center will not begin untill all work is done on south side.