Inspections for the day of: Tuesday, June 11, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-01046 General Inspection6/11/20196/11/20196/11/2019 2:37:49 PM PASS
Backyard is landscaped. Work on driveway out front.
Crestline sewer work is currently in front of home.
ESC18-00792 General Inspection6/11/20196/11/20196/11/2019 1:04:49 PM PART
Lots of blowing dust. Crews are prepping parking lot, graders and track steer on site moving material. Large piles of pit run. Building construction looks complete on exterior. Parking lot has curbing and islands complete. Water meter connected to hydrant, did not see any water wagon on site.
ESC19-00502 Site Final6/11/20196/11/20196/11/2019 12:42:28 PMPPASS
ESC19-00351 General Inspection6/11/20196/11/20196/11/2019 12:36:47 PMPPASS
WIP on sewer in road in front of site. No new activity, site is exposed, water truck on site.
ESC18-00983 General Inspection6/11/20196/11/20196/11/2019 12:06:11 PMPPASS
Sidewalks have been installed, road bed prepped. No dust or ESC issues.
ESC19-00371 General Inspection6/11/20196/11/20196/11/2019 10:21:26 AMPPASS
Water truck on site, no blowing dust. No trackout or ESC issues.
ESC16-00225 General Inspection6/10/20196/11/20196/11/2019 10:20:52 AMPPASS
No new homes, all lots have good coverage.
ESC17-01749 General Inspection6/11/20196/11/20196/11/2019 10:16:22 AM PASS
Landscapers on site. Home is nearly completed. Looks like trash cleaned off hillside below.
ESC17-00791 BMP Violation6/11/20196/11/20196/11/2019 10:08:51 AMPFAIL
Still a rill and debris in neighbors yard. Witches hat on drain has failed and fallen into drain, some sediment also in drain. RP has been notified many times about site.
ESC17-00078 General Inspection6/10/20196/11/20196/11/2019 9:55:06 AMAPASS
Silt fence along Warm Springs on east end of project, landscaping begun on west side. Every home under construction has trash box. Roads within site are clean, neighborhood washout in good shape. Some trash has blown around site.