ESC19-00916
| General Inspection | 6/8/2020 | 6/8/2020 | 6/9/2020 12:10:27 PM | | PASS |
|
|
No disturbances. Can't tell if work finished or hasn't begun.
|
ESC19-00935
| General Inspection | 6/5/2020 | 6/8/2020 | 6/9/2020 11:52:13 AM | P | PASS |
|
|
No new activity at site, starting to overgrow
|
ESC20-00343
| Site Final | 6/8/2020 | 6/8/2020 | 6/9/2020 11:26:35 AM | P | PASS |
|
|
|
ESC19-00882
| General Inspection | 6/8/2020 | 6/8/2020 | 6/9/2020 11:17:45 AM | | PASS |
|
|
Work completed, DI protection still installed.
|
ESC16-00406
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 2:15:54 PM | P | PASS |
|
|
Site is clean. No issues with any of the building lots.
|
ESC18-00498
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 2:13:27 PM | P | PART |
|
|
Some small rills left sand on road and sidewalk. No major issues, rills are right next to job trailer.
|
ESC19-00994
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 1:59:29 PM | P | PART |
|
|
Issues where water has come of Bogus Basin rd. Rills down embankment, sediment and water going through culvert and causing issues. Lot is good and stable.
|
ESC19-00702
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 1:58:37 PM | P | PART |
|
|
Met with Scott at site. Some rilling coming down middle where sewer was ran. Already on site with skid steer to make repairs. Walking path was blown out from water coming through culvert.
|
ESC19-00770
| DOC - Permit Finaled | 6/8/2020 | 6/8/2020 | 6/8/2020 11:28:33 AM | P | PASS |
|
|
Landscaping completed.
|
ESC17-00842
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 11:18:17 AM | P | PASS |
|
|
No issues with site. Individual lots will be dealt with.
|
ESC20-00214
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 11:17:48 AM | P | FAIL |
|
|
Used silt fence for washout, allows water to seep through. Message sent to RP to clean it up and install leak proof washout. Follow up scheduled.
|
ESC18-01116
| Aging Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 10:59:10 AM | | PASS |
|
|
Addition is all framed and contained in yard. Area is clean, outdide disturbances completed.
|
ESC18-01118
| Aging Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 10:52:01 AM | | PASS |
|
|
Site has had topsoil brought and is prepped for landscaping. Site is clean.
|
ESC19-00920
| DOC - Permit Finaled | 6/8/2020 | 6/8/2020 | 6/8/2020 10:27:19 AM | P | PASS |
|
|
|
ESC19-00715
| DOC - Permit Finaled | 6/8/2020 | 6/8/2020 | 6/8/2020 10:27:11 AM | P | PASS |
|
|
|
ESC19-00435
| DOC - Permit Finaled | 6/8/2020 | 6/8/2020 | 6/8/2020 10:10:20 AM | P | PASS |
|
|
|
ESC19-00435
| DOC - Permit Finaled | 6/8/2020 | 6/8/2020 | 6/8/2020 10:09:54 AM | P | PASS |
|
|
|
ESC19-00923
| DOC - Permit Finaled | 6/8/2020 | 6/8/2020 | 6/8/2020 10:09:42 AM | P | PASS |
|
|
|
ESC17-00078
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 10:08:42 AM | | PASS |
|
|
Finishing up on last few homes. All are framed, one still needs some stucco. Landscapers working at site on finished homes. Nonlandscaped lots are dirty but contained.
|
ESC19-01581
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 9:56:00 AM | P | PASS |
|
|
Lots of fill has brought up elevation of site. Lots of standing water in lot to north, do not know if it has been an issue before, just noting.
|
ESC19-01072
| Site Final | 6/5/2020 | 6/8/2020 | 6/8/2020 9:37:29 AM | P | PASS |
|
|
|
ESC18-01089
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 9:37:16 AM | | PASS |
|
|
Foxgrove is clean. Trash crew on site cleaning up. Laqndscapers were active, equipment sitting idle. No issues on phase.
|
ESC18-00020
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 9:36:26 AM | | PART |
|
|
Lots of trackout coming from 6007 Hootowl, lot is not active and has no permit. Rest of site clean, message sent to Kyle
|
ESC18-00164
| General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 9:11:18 AM | P | PASS |
|
|
No issues from rainfall. Looks like it stayed on tiers and seeped in. Road is clean. AME electric crew on site.
|