Inspections for the day of: Monday, July 16, 2018.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00392 General Inspection7/16/20187/16/20187/18/2018 3:03:56 PM PASS
Site is contained. Goodman St is now patched. No ESC issues at site.
ESC16-00489 General Inspection7/16/20187/16/20187/18/2018 1:33:44 PM PASS
Phase nearly complete. Neighborhood BMPs still in place.
ESC18-00498 General Inspection7/16/20187/16/20187/16/2018 3:18:52 PMPPASS
Grading in progress. Water truck on site keeping site moist and dust free. All construction equipment staying in work area, no track out.
ESC16-00406 General Inspection7/6/20187/16/20187/16/2018 2:32:38 PMAPASS
Neighborhood is in good shape. Each home is displaying permit and is responsible for their own BMPs. Phase 2 grading is underway.
ESC17-00636 Aging Inspection7/16/20187/16/20187/16/2018 12:57:59 PM CANC
ESC17-00636 DOC - Permit Finaled7/16/20187/16/20187/16/2018 12:57:52 PMPPASS
ESC17-01009 General Inspection7/16/20187/16/20187/16/2018 12:57:14 PM PASS
Work hasn't begun.
ESC17-00471 Aging Inspection7/16/20187/16/20187/16/2018 12:25:03 PM PASS
No new activity, lot is still being used for storage. Wattle on north end is old and will need to be replaced before any new dirt work.
ESC18-00222 General Inspection7/16/20187/16/20187/16/2018 12:07:44 PMPPASS
Working on excavation for seepage bed. Area will also be getting sidewalk and paved road. Work will be finished before school begins.
ESC18-00546 General Inspection7/16/20187/16/20187/16/2018 11:57:40 AMPPASS
First section of foundation has been poured, eco pan on site. No dirt leaving limits of disturbance, no dust issues. Water truck is on site. All vehicles being parked in paved parking lot.
ESC17-00619 General Inspection7/16/20187/16/20187/16/2018 11:44:22 AM CANC
ESC17-00619 DOC - Permit Finaled7/16/20187/16/20187/16/2018 11:44:16 AMPPASS
ESC18-00576 General Inspection7/16/20187/16/20187/16/2018 11:28:41 AMPPASS
Parking lot addition complete. Gator guard and gravel snake bags still protecting site.
ESC18-00369 General Inspection7/16/20187/16/20187/16/2018 11:21:19 AMPPASS
Excavation has begun, pile of backfill on southern part of property. No ESC issues, site contained.
ESC17-01598 Site Final7/16/20187/16/20187/16/2018 11:12:34 AMPPASS
ESC17-01011 General Inspection7/16/20187/16/20187/16/2018 10:57:25 AM PASS
Site is clean and contained. Cinder block work complete, will be no more block cutting. Small area of sidewa;lk scheduled to be poured today. No trackout or blowing dust.
ESC16-01189 General Inspection7/16/20187/16/20187/16/2018 9:29:24 AM PASS
Witches hat still in on Preece, everything else on site complete.
ESC16-01580 Aging Inspection7/16/20187/16/20187/16/2018 9:14:28 AM CANC
ESC16-01580 DOC - Permit Finaled7/16/20187/16/20187/16/2018 9:14:19 AMPPASS