Inspections for the day of: Friday, July 27, 2018.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00640 General Inspection7/27/20187/27/20187/27/2018 1:48:40 PM PASS
Outside still disturbed but stable, no issues.
ESC16-00617 General Inspection7/27/20187/27/20187/27/2018 1:48:40 PM PASS
Work on interior.
ESC16-01722 General Inspection7/27/20187/27/20187/27/2018 12:22:27 PM CANC
ESC16-01723 General Inspection7/27/20187/27/20187/27/2018 12:21:55 PM CANC
ESC16-01723 DOC - Permit Finaled7/27/20187/27/20187/27/2018 12:21:30 PMPPASS
ESC16-01722 DOC - Permit Finaled7/27/20187/27/20187/27/2018 12:21:17 PMPPASS
ESC18-01075 Site Preparation7/27/20187/27/20187/27/2018 11:53:48 AMPPASS
Staging is off of troutner.Some trenching along troutner, work is headed up table rock. Table rock iscurrently excavated with material stored on street. Vac truck is on site, drain inlets '
protected.
ESC17-00013 General Inspection7/27/20187/27/20187/27/2018 11:17:20 AM PASS
Still idle, no work has begun. Washouts on sight, roads are clean.
ESC17-01037 Aging Inspection7/27/20187/27/20187/27/2018 10:59:44 AM CANC
ESC17-01036 Aging Inspection7/27/20187/27/20187/27/2018 10:59:35 AM CANC
ESC17-01036 DOC - Permit Finaled7/27/20187/27/20187/27/2018 10:59:25 AMPPASS
ESC17-01037 DOC - Permit Finaled7/27/20187/27/20187/27/2018 10:59:11 AMPPASS
ESC17-00648 General Inspection7/27/20187/27/20187/27/2018 10:49:40 AM PART
Working on stucco. Some material buckets and waste laying around home.
ESC15-00556 General Inspection7/27/20187/27/20187/27/2018 10:45:34 AM PASS
Last few homes on Taboo under construction. Site is clean. When Taboo done and neighborhood BMPs all removed ok to close permit.