Inspections for the day of: Friday, August 23, 2019.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-01451 General Inspection8/23/20198/23/20198/26/2019 12:16:36 PM PASS
Hydro seeder on site. Driveway is still gravel.
ESC18-01467 General Inspection8/23/20198/23/20198/23/2019 1:38:55 PM DEFR
No workers at site, fence to backyard.
ESC19-00770 General Inspection8/19/20198/23/20198/23/2019 1:30:10 PMPPART
Concrete washout is overflowing.
ESC18-01333 General Inspection8/23/20198/23/20198/23/2019 11:52:41 AM PASS
Crew has just finished prepping base for driveway. They are sweeping off road and sidewalk. Exterior looks completed, lot still has not stabalization.
ESC18-01480 General Inspection8/23/20198/23/20198/23/2019 11:45:16 AM CANC
ESC18-01480 DOC - Permit Finaled8/23/20198/23/20198/23/2019 11:45:07 AMPPASS
ESC18-01060 Aging Inspection8/23/20198/23/20198/23/2019 11:38:19 AM PASS
Construction work looks completed, back yard is not landscaped.
ESC19-00238 General Inspection8/23/20198/23/20198/23/2019 11:19:31 AMPPASS
ESC18-01687 General Inspection8/23/20198/23/20198/23/2019 11:19:11 AMPPASS
Paving crew working on pump tracks, concrete crew on sidewalks. Sites are contained, no ESC issues.
ESC19-00788 General Inspection8/23/20198/23/20198/23/2019 11:18:29 AMPPASS
Site prep looks completed for archery range. Site in contained. Police range still not demoed, lots of pallets of old rotting sandbags on site.
ESC18-01241 Aging Inspection8/23/20198/23/20198/23/2019 11:00:28 AM CANC
ESC18-01241 DOC - Permit Finaled8/23/20198/23/20198/23/2019 11:00:23 AMPPASS
ESC18-01196 Site Final8/21/20198/23/20198/23/2019 10:19:41 AMPPASS
ESC18-01053 General Inspection8/23/20198/23/20198/23/2019 10:12:27 AMPFAIL
Landscapers have topsoil and rocks stored on road, lots of tracking everywhere.
Rollpan on site and being used. Some builders better at keeping clean site.
ESC19-00401 General Inspection8/23/20198/23/20198/23/2019 9:56:03 AMPPASS
Road and sidewalks now completed. Crew on site finishing last 6' section of sidewalk. Street and sidewalk swept, access blocked from Milwaukee.
ESC18-00301 General Inspection8/23/20198/23/20198/23/2019 9:54:09 AM PASS
No new activity, still idle. People are parking on lot.
ESC19-00678 General Inspection8/23/20198/23/20198/23/2019 9:38:31 AMPPASS
Knife River on site doing some trenching and work at sidewalk. Equipment mobolized but not active. Site still hasn't been stripped.
ESC18-01233 Aging Inspection8/23/20198/23/20198/23/2019 9:26:44 AM PASS
No visible disturbances.
ESC18-01489 Site Final8/23/20198/23/20198/23/2019 9:17:52 AMPPASS
complete with temporary BMPs removed?