Inspections for the day of: Wednesday, August 7, 2019.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-00236 Aging Inspection8/7/20198/7/20198/8/2019 11:33:51 AM CANC
ESC17-00692 Site Final8/5/20198/7/20198/8/2019 9:59:57 AMAPASS
BLD permit has been voided. Change of contractor...check for issues and close
ESC19-00371 General Inspection8/2/20198/7/20198/8/2019 9:47:54 AMAPART
Wind is blowing towards neighborhood today. Two water trucks running on site, still some dust. Sand rock seperator also running and being water, causing some dust. Water trucks are still going to warm springs for water, no plan to bring tank to site. Some trackout, let foreman know that track pad needs to be cleaned. All workers parking on road.
Major source of dust is lower haul road, has been saturated with water, dust is very fine. Site has lots of disturbed area and very loose dust, like talcum powder.
3 area of blasting remain. Some sort of temporary stabalization should be considered on idle areas.
ESC19-00396 Conference8/7/20198/7/20198/7/2019 3:47:07 PMPDONE
Met with developer and concerned neighbor.
Met with neighbor earlier in day. Dust is on porch and accumlates on windows and trim. AC filters need to be cleaned weekly.
Main issue is dust. Material is being stockpiled and hauled off, currently skid steer is broken down and work is on hold.
Technically contractor has 2 weeks to stabalize stockpile. Material has been removed and added so stockpile is still being worked, has not been 2 weeks.
Neighbor and contractor could not come to any agreement.
Correction request made:
1. Sweep sidewalk and approach at end of each work day.
2. Repair and add to construction entrance.
3. Build construction waste box
4. Use water to control dust.
Given 1 week to comply.
ESC18-00658 Aging Inspection8/7/20198/7/20198/7/2019 3:16:43 PM PASS
Landscaping not completed.
ESC18-01171 General Inspection8/7/20198/7/20198/7/2019 3:01:09 PM PASS
Some trench work on site. Lots of disturbed area, landscapers also on site. Lot looks like it is being graded for completion, nothing leaving site.
ESC17-00315 General Inspection8/7/20198/7/20198/7/2019 2:20:02 PM CANC
ESC17-01009 General Inspection8/7/20198/7/20198/7/2019 12:27:51 PM PASS
Site is contained, fence is up. All access to site now comes from above an Collister.
ESC15-00853 General Inspection8/7/20198/7/20198/7/2019 12:27:40 PM DONE
entry error
ESC18-01284 General Inspection8/7/20198/7/20198/7/2019 12:26:57 PM PART
Materials still stored in road. Drywall work has begun, scraps piled in front of home. Road is dirty.
ESC17-01287 General Inspection8/7/20198/7/20198/7/2019 12:21:36 PM PASS
Hillside has been tackified/seeded.
ESC18-01447 General Inspection8/7/20198/7/20198/7/2019 11:40:28 AM FAIL
Site needs trashbox and someone missed washout. Sent message to RP, follow up scheduled.
ESC19-00304 General Inspection8/7/20198/7/20198/7/2019 10:58:03 AMPPASS
WIP on utilities. Excavators and loaders on site, material is being hauled off. Water truck on site spraying. Some tracking onto lake hazel, road is closed. Water truck is spraying stockpiles.
ESC19-00303 General Inspection8/7/20198/7/20198/7/2019 10:56:34 AMPPASS
Only some drilling on side of project. lake hazel is closed for utilities. Crew on site doing maintenance to drill rig. No site entrance on Lake Hazel, access is from neighborhood.
ESC18-01444 General Inspection8/7/20198/7/20198/7/2019 9:52:33 AM FAIL
Multiple piles of uncontained washout, building debris laying around, streets need to be cleaned.
Corrective action request will be sent to RP, follow up scheduled.