ESC17-01754
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 3:54:38 PM | P | PASS |
|
|
Sweeper will come through and clean up street. Trench will be ran through entrance for power, will rebuild when trench completed. Water truck on site, some dust.
|
ESC17-01211
| Aging Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 3:06:22 PM | | CANC |
|
|
|
ESC17-01211
| DOC - Permit Finaled | 9/11/2018 | 9/11/2018 | 9/11/2018 3:05:53 PM | P | PASS |
|
|
|
ESC18-00498
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 2:51:32 PM | P | PASS |
|
|
Crushed rock entrances installed. Hillsides have been tracked, tackified, and wattle installed. Prep for waterline installation.
|
ESC13-00806
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 2:45:53 PM | | CANC |
|
|
|
ESC17-00842
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 12:48:31 PM | | PASS |
|
|
Only one active home site, has cleaned issues from last inspection. Site is stable and idle.
|
ESC17-01024
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 12:35:10 PM | P | CANC |
|
|
|
ESC17-01024
| DOC - Permit Finaled | 9/11/2018 | 9/11/2018 | 9/11/2018 12:35:00 PM | P | PASS |
|
|
Expired
|
ESC17-01024
| Aging Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 12:30:51 PM | | CANC |
|
|
Entry error
|
ESC18-00349
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 12:30:13 PM | P | PASS |
|
|
Work has begun on roads inside of development. Parts of Breneman have been removed and will need to be repaved. Lots of dirt is on 32nd, sweeper should be there late today or in the morning.. Wood Bros on site doing walk through. Sewer rings on 32nd still not completed, blocked by candles.
|
ESC17-01111
| Aging Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 11:51:42 AM | | FAIL |
|
|
No permit displayed. Washout has been dumped in front of lot, no containment. Trash is piled on site, no containment.
|
ESC18-01053
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 11:38:53 AM | P | PASS |
|
|
No current activity. Site will need a proper construction entrance before building.
|
ESC18-00659
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 11:15:53 AM | P | PART |
|
|
Currently only activity is an excavato trenching for utilities. Water truck on site, no dust. No permiter BMPs along road, no DI protection in Cul-de-sac. Construction entrance currently has trench running through it. Green permit sign hasn't been posted at front SWPPP sign.
|
ESC17-01172
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:49:27 AM | P | PASS |
|
|
Building and landscaping all complete. After work on interior is finished and job trailer removed will check for final.
|
ESC18-00063
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:32:58 AM | P | PASS |
|
|
Parking lot complete and landscaped. Area where job trailer was and off to side of project still bare.
|
ESC15-00306
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:06:57 AM | | PASS |
|
|
Starting to install BMPs and site prep for next phase. Will call in for thorough walkthrough when everything installed and ready.
|
ESC17-01132
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 9:39:54 AM | P | PASS |
|
|
Site clean. Work on extending sidewalk down Jefferson to WWP Blvd, will remove wattle from that area when complete. Area along WWP Blvd has a small buffer and wattles. Staging is on east side of project. No dust or trackout issues.
|
ESC18-00740
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 9:10:36 AM | P | PASS |
|
|
No outside disturbances.
|