ESC17-00791
| General Inspection | 9/27/2019 | 9/27/2019 | 9/30/2019 10:31:00 AM | | PASS |
|
|
Site is stable, no esc issues. Good growth covering area.
|
ESC18-01428
| Site Final | 9/24/2019 | 9/27/2019 | 9/30/2019 9:16:10 AM | P | PASS |
|
|
|
ESC18-01427
| Site Final | 9/24/2019 | 9/27/2019 | 9/30/2019 9:15:51 AM | P | PASS |
|
|
|
ESC18-01344
| Aging Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 1:42:46 PM | | CANC |
|
|
|
ESC18-01344
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 1:42:41 PM | P | PASS |
|
|
|
ESC18-01574
| Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 1:39:49 PM | P | NR |
|
|
Side lot still bare.
|
ESC18-01558
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 12:05:35 PM | | PASS |
|
|
No issues on site.
|
ESC19-00091
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 12:05:13 PM | P | PASS |
|
|
WIP on framing. Pool and rockwork in back are completed. No esc issues.
|
ESC18-01576
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 12:04:20 PM | | PASS |
|
|
All current work is interior. Lot still bare, bmps installed, no esc issues.
|
ESC18-01115
| Aging Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 11:41:12 AM | | PASS |
|
|
Home exterior and driveway completed, still needs landscaping. Pile of landscape rocks on road. 2 homes share common drive.
|
ESC19-00443
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 11:21:30 AM | P | PASS |
|
|
Home exterior completed. Only home in development. No landscaping or stabalization. No trackout onto pierce.
|
ESC19-00076
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 11:20:43 AM | P | PASS |
|
|
Met with ESI on site. Only issue is to repair and turn entrance so it is not so compacted. Masons and concrete crews using washouts. All material, trash, and recycling is on rear of lot.
|
ESC19-00506
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 11:19:27 AM | P | PASS |
|
|
Sewer work and dewatering completed. Site is currently inactive. Stabalized entrance leading to castle, no trackout. Two pieced of equipment stored at site. Ground is crusted over from rain, no blowing dust. Met with owner, plan is to get water next week and then joint trench. Will go straight to curb and gutter and plan to be paved before winter and repair daycare parking lot.
|
ESC19-01106
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 10:55:19 AM | P | PASS |
|
|
Sewer work done, trenches filled. No activity at site.
|
ESC17-01479
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 10:46:39 AM | P | PASS |
|
|
WIP on two homes, 1 vacant lot. Site is clean and mostly complete. No esc issues.
|
ESC19-00405
| Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 10:42:16 AM | P | PASS |
|
|
|
ESC18-01790
| Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 10:41:57 AM | P | PASS |
|
|
|
ESC18-01790
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:41:44 AM | P | PASS |
|
|
|
ESC18-01371
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:17:37 AM | P | PASS |
|
|
|
ESC18-01391
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:17:30 AM | P | PASS |
|
|
|
ESC18-01388
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:17:23 AM | P | PASS |
|
|
|
ESC18-01389
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:17:15 AM | P | PASS |
|
|
|
ESC18-01384
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:17:07 AM | P | PASS |
|
|
|
ESC18-01724
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:16:44 AM | P | PASS |
|
|
|
ESC18-01382
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:16:35 AM | P | PASS |
|
|
|
ESC18-01381
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:16:25 AM | P | PASS |
|
|
|
ESC18-01380
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:16:17 AM | P | PASS |
|
|
|
ESC18-01379
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:16:02 AM | P | PASS |
|
|
|
ESC18-01378
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:15:53 AM | P | PASS |
|
|
|
ESC18-01369
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:15:44 AM | P | PASS |
|
|
|
ESC18-01725
| Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 10:15:13 AM | P | CANC |
|
|
|
ESC18-01385
| Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 10:15:03 AM | P | CANC |
|
|
close all ESC permits that are finished on Tarako
|
ESC18-01727
| Site Final | 9/27/2019 | 9/27/2019 | 9/27/2019 10:14:52 AM | P | CANC |
|
|
|
ESC18-01725
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:14:44 AM | P | PASS |
|
|
|
ESC18-01385
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:14:33 AM | P | PASS |
|
|
|
ESC18-01727
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 10:14:26 AM | P | PASS |
|
|
|
ESC18-01496
| Aging Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 9:46:21 AM | | CANC |
|
|
|
ESC18-01496
| DOC - Permit Finaled | 9/27/2019 | 9/27/2019 | 9/27/2019 9:46:13 AM | P | PASS |
|
|
|
ESC19-00034
| BMP Violation | 9/24/2019 | 9/27/2019 | 9/27/2019 9:40:31 AM | A | PASS |
|
|
Street swept and inlet protection installed. Dirt on road will be an issue until the areas cut out for water and sewer are patched.
|
ESC16-00625
| General Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 8:32:26 AM | | PASS |
|
|
Home and landscaping completed.
|