Inspections for the day of: Wednesday, September 11, 2019.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Scharfen
TitleFIRE CODE PLAN EXAMINER
Phone #208-608-7110
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00677 INSP-Alarm Testing9/11/20199/11/20199/11/2019 3:41:28 PMPPASS
Tested fire alarm. New devices work and function correctly.

after 330 //John Phone #: ###-####
FIR19-00570 INSP-Sprinkler Rough-in/Hydro9/11/20199/11/20199/11/2019 2:53:24 PMPPASS
restroom area ok for cover. noted on site plans area verified. 8 heads.

Mike Phone #: ###-####
BLD19-03073 FIRE-Final Inspection9/11/20199/11/20199/11/2019 2:29:37 PMPFAIL
Main exit exit light needs serviced. Door hardware and fire extinguisher all look good.
BLD18-04252 FIRE-Final Inspection9/11/20199/11/20199/11/2019 2:14:30 PMPPASS
Vanilla finish. Passed inspection. No occupancy on this permit.

fire/life ; safety, shell/core building Phone #: ###-#### Inspection requested via web by J.C. Murray
FIR19-00163 INSP-Final Inspection9/10/20199/11/20199/11/2019 12:00:00 AMAFAIL
Plans do not match what is installed. Plans show two phone lines for monitoring. There is a DSC Cell DACT installed that is not on plans. According to JCI this was installed by Apex. Did not check horn strobe placment/candella. THere is an in duct detector in the reception area that is above hard lid ceiling with no access hatch. Per Brian, he accessed by moving the 120V lighting. I noted there were at least 4 card readers (not live) by entry doors and there is no access control interface shown on fire alarm plans. While access control integration with fire alarm wouldn't hold up fire alarm final it may hold up building life safety. I gave this information verbally to both Damien over the phone and Brian, both with JCI. General Contractor was not on site.

Call ahead to Brian ###-#### Phone #: ###-#### >> Inspection requested via web by Kristin Dolan
FIR19-00237 INSP-Final Inspection9/10/20199/11/20199/11/2019 12:00:00 AMAPASS
Tested tampers and flow switch interface with fire alarm system. Checked escutcheons. Outside bell functions. Passed. Thank-you!

Please Txt Tyler Loomis ###-#### 30 min prior to Final Insp start if you can not txt him please call Ken Orahood ###-#### and he will contact Tyler.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank