BLD-Final | 2/28/2012 | 2/28/2012 | 2/28/2012 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 2/15/2012 | 2/17/2012 | 2/17/2012 | P | PASS |
Tom Arcoraci
|
|
|
>> Inspection requested via web by bryan everman
|
BLD-Final | 2/16/2012 | 2/17/2012 | 2/17/2012 | A | PART |
Tom Arcoraci
|
|
|
>> Inspection requested via web by bryan everman
|
BLD-Final | 2/16/2012 | 2/16/2012 | 2/16/2012 | P | PART |
Tom Arcoraci
|
|
|
>> Inspection requested via web by bryan everman spec insp and eng sign off ok when elec final and front doors installed ok for perm occ ok for temp
|
FIRE-Final Inspection | 2/16/2012 | 2/16/2012 | 2/16/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Alarm Testing | 2/15/2012 | 2/16/2012 | 2/16/2012 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 2/15/2012 | 2/16/2012 | 2/16/2012 | A | CANC |
Troy Cobbley
|
|
|
>> Inspection requested via web by bryan everman Inspection cancelled from web by: bryan everman
|
FIRE-Final Inspection | 2/15/2012 | 2/16/2012 | 2/16/2012 | P | CANC |
Troy Cobbley
|
|
|
>> Inspection requested via web by bryan everman Inspection cancelled from web by: bryan everman
|
FIRE-Final Inspection | 2/15/2012 | 2/17/2012 | 2/16/2012 | A | CANC |
Troy Cobbley
|
|
|
>> Inspection requested via web by bryan everman Inspection cancelled from web by: bryan everman
|
FIRE-Final Inspection | 2/15/2012 | 2/15/2012 | 2/16/2012 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits addressed. Need the building address posted and the signage provided for the fire sprinkler and fire alarm control panel rooms posted. Need to verify that Chad mounted the knox box.
|
FIRE-Alarm Testing | 2/15/2012 | 2/15/2012 | 2/15/2012 | P | DONE |
Troy Cobbley
|
|
|
The fire alarm testing is complete except for a copy of the signal reports.
|
BLD-Other | 1/30/2012 | 1/30/2012 | 1/30/2012 | P | PASS |
Tom Arcoraci
|
|
|
ceiling cover Phone #: ###-#### >> Inspection requested via web by bryan everman
|
BLD-Wall cover | 12/29/2011 | 12/29/2011 | 12/29/2011 | P | PASS |
Jim Storey
|
|
|
Main entry soffit framing Phone #: ###-#### >> Inspection requested via web by bryan everman
|
BLD-Wall cover | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Tom Arcoraci
|
|
|
west side and entry >> Inspection requested via web by bryan everman
|
BLD-Wall cover | 12/1/2011 | 12/2/2011 | 12/2/2011 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by bryan everman
|
BLD-Wall cover | 11/30/2011 | 11/30/2011 | 11/30/2011 | P | PASS |
Tom Arcoraci
|
|
|
Shear walls and south east corner of building Phone #: ###-#### >> Inspection requested via web by bryan everman needs anchor bolts tma
|
BLD-Other | 11/23/2011 | 11/28/2011 | 11/28/2011 | P | CANC |
Tom Arcoraci
|
|
|
Shear wall inspection Phone #: ###-#### >> Inspection requested via web by bryan everman Inspection cancelled from web by: bryan everman
|
BLD-Framing/Rough-in | 11/16/2011 | 11/17/2011 | 11/17/2011 | A | PASS |
Tom Arcoraci
|
|
|
ross Phone #: ###-#### north end of north south building ok for cover
|
BLD-Wall Bracing | 11/15/2011 | 11/15/2011 | 11/15/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 11/11/2011 | 11/14/2011 | 11/14/2011 | A | PASS |
Tom Arcoraci
|
|
|
Framing RI and shear nailing and roof nailing Phone #: ###-#### >> Inspection requested via web by bryan everman
|
BLD-Other | 11/11/2011 | 11/14/2011 | 11/14/2011 | P | CANC |
Tom Arcoraci
|
|
|
Exterior wall cover inspection and roof nailing inspection Phone #: ###-#### >> Inspection requested via web by bryan everman Inspection cancelled from web by: bryan everman
|
BLD-Other | 10/31/2011 | 11/2/2011 | 11/3/2011 | A | PASS |
Tom Arcoraci
|
|
|
ok to wrap
|
BLD-Other | 10/31/2011 | 10/31/2011 | 10/31/2011 | P | PASS |
Tom Arcoraci
|
|
|
Bryan Everman Roof nailing and shear nailing inspection Phone #: ###-#### >> Inspection requested via web by bryan everman
|
BLD-Framing/Rough-in | 10/21/2011 | 10/24/2011 | 10/24/2011 | A | PART |
Tom Arcoraci
|
|
|
bruce Phone #: ###-#### roof ok for cover east side
|
FIRE-Conference | 10/21/2011 | 10/21/2011 | 10/21/2011 | P | DONE |
Troy Cobbley
|
|
|
I stopped at the job site and found that the "dog house" has been provided as well as heat. This temporary set up is acceptable as previously discussed.
|
FIRE-Conference | 10/18/2011 | 10/18/2011 | 10/18/2011 | P | DONE |
Troy Cobbley
|
|
|
I stopped today at Bishop Kelly High School to verify that the "dog house", with heat, had been installed over the sprinkler supply piping. It has not. The piping has been wrapped with concrete blankets which I remember was not an option. The openings along the existing wall are covered with plastic but no heat for the space has been provided.
|
FIRE-Conference | 10/11/2011 | 10/11/2011 | 10/11/2011 | A | DONE |
Troy Cobbley
|
|
|
Romeo Gervais and I met with Chad and Rich Raimondi, with Bishop Kelly, about the need for protection of both the fire sprinkler and fire alarm systems that are exposed to the elements. It was agreed that steps would be taken starting today and completed by the end of the week. Chad said he would follow up with me later in the week at which time I will perform a courtesy inspection.
|
BLD-Framing/Rough-in | 10/10/2011 | 10/10/2011 | 10/10/2011 | P | PART |
Tom Arcoraci
|
|
|
ross Phone #: ###-#### king studs 16 oc screw ok
|
BLD-Footing | 8/26/2011 | 8/29/2011 | 8/29/2011 | A | PART |
Tom Arcoraci
|
|
|
ross - rebar - pouring at 3 Phone #: ###-#### special insp req by plans
|