FIRE-Final Inspection | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Jim Sly
|
|
|
call before to meet//late as poss//Ken Phone #: ###-#### Certificate of Compliance issued.
|
DOC - Permit Finaled | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Conference | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | DONE |
Troy Cobbley
|
|
|
Tenant space 206 and the main lobby up to the stairs is complete. Per the insulation contractor space 204 was done previously by an unknown contractor.
|
BLD-Framing/Rough-in | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | PART |
Jim Sly
|
|
|
Main lobby OK up to stairway...Room 208 OK Rooms 206 and 204 previously completed.
|
FIRE-Final Inspection | 7/13/2012 | 7/13/2012 | 7/13/2012 | P | CANC |
Troy Cobbley
|
|
|
Per Tom the contractor is unable to be on site. Please reschedule for monday.
|
BLD-Framing/Rough-in | 7/13/2012 | 7/13/2012 | 7/13/2012 | P | DEFR |
Tom Arcoraci
|
|
|
ken Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 7/5/2012 | 7/5/2012 | 7/5/2012 | P | PASS |
Troy Cobbley
|
|
|
The insulation backing in Suite 101 (book store) is complete
|
BLD-Other | 7/5/2012 | 7/5/2012 | 7/5/2012 | P | PART |
Jim Sly
|
|
|
ken Phone #: ###-#### Bookstore completed.
|
FIRE-Final Inspection | 6/5/2012 | 6/5/2012 | 6/5/2012 | P | CANC |
Troy Cobbley
|
|
|
unit 208 - -Ken Phone #: ###-#### - Inspection canceled per phone conversation with Jim Sly. Project is not ready for inspection. Inspection will be scheduled for next monday.
|
BLD-Final | 6/5/2012 | 6/5/2012 | 6/5/2012 | P | CANC |
Jim Sly
|
|
|
Unit 208 - - Ken Phone #: ###-####
|
FIRE-Final Inspection | 6/4/2012 | 6/4/2012 | 6/4/2012 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was actually for a conference. I met Jim Sly at the project site as well as the insulator contractor and discussed what jim and I would be looking for on our inspections. This included sprinkler obstructions. Work is being started in the Windmill book store.
|
BLD-Final | 6/4/2012 | 6/4/2012 | 6/4/2012 | P | PEND |
Jim Sly
|
|
|
brandon Phone #: ###-#### Had meeting with Workers to explain what we are looking for at final insp.
|
BLD-Conference | 5/23/2012 | 5/30/2012 | 5/30/2012 | A | DONE |
Jim Sly
|
|
|
ken Phone #: ###-#### Met with G&G Matter Architects to discuss plan to protect all Kraft faced insulation.
|