BLD-Final | 10/31/2013 | 11/1/2013 | 11/1/2013 | P | PASS |
Mike Jordan
|
|
|
mike Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 10/31/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 9/19/2013 | 9/20/2013 | 9/20/2013 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. ok to occupy service bay expansion.
|
FIRE-Final Inspection | 9/19/2013 | 9/20/2013 | 9/20/2013 | A | CANC |
Troy Cobbley
|
|
|
A partial already given for these areas. Waiting for fire alarm to be finished.
|
FIRE-Final Inspection | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | PART |
Troy Cobbley
|
|
|
Life safety in the Service Bay expansion is passed.
|
FIRE-Final Inspection | 8/29/2013 | 8/30/2013 | 8/30/2013 | A | PART |
Troy Cobbley
|
|
|
The fire doors in the Lube Bay and the new Service Shop passed inspection. Links are on both sides of the wall and at the deck.
|
BLD-Final | 8/27/2013 | 8/28/2013 | 8/28/2013 | A | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Temp. final on lube and wash only.
|
FIRE-Final Inspection | 8/27/2013 | 8/27/2013 | 8/27/2013 | P | PART |
Troy Cobbley
|
|
|
Lube Bay and Car Wash life safety complete. The fire door between the Lube Bay and the existing shop area shall remain locked until door has been tested and passed. As of now there are no "links" for activation installed on both sides of the wall at the roof deck as required in NFPA 80.
|
FIRE-Final Inspection | 8/22/2013 | 8/23/2013 | 8/23/2013 | P | PART |
Troy Cobbley
|
|
|
todays inspection was for the Lube Bay and the Service Shop expansion. The life safety will be complete in the Lube Bay when an additional fire extinguisher is provided in the pit and the car wash and the fire door linkages have been installed and tested. The Service Shop life safety needs the fire doors addressed and exit signs, emergency lights and exit discharge lighting provided. This is based on the occupant load exceeding 29 people. See IFC table 1021.2, and 1006.1.
The Lexus drive through is complete as well and can be used.
|
BLD-Framing/Rough-in | 7/19/2013 | 7/19/2013 | 7/19/2013 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/18/2013 | 7/19/2013 | 7/19/2013 | A | PASS |
Tom Arcoraci
|
|
|
mike Phone #: ###-####
|
BLD-Other | 6/13/2013 | 6/13/2013 | 6/13/2013 | P | PART |
Mike Jordan
|
|
|
grouting at 1:30 - masonary grouting - Mike Phone #: ###-####. top of wall west wall for west shop addition. Special inector on site. Work in progress.
|
BLD-Other | 6/7/2013 | 6/7/2013 | 6/7/2013 | P | NR |
Mike Jordan
|
|
|
No masonry today.
|
BLD-Other | 6/5/2013 | 6/5/2013 | 6/5/2013 | P | PART |
Mike Jordan
|
|
|
masonary grout//Mike Phone #: ###-####. Work in progress, 16ft. to 20ft. elevation for shop expansion. Special inspector on site.
|
BLD-Other | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | CANC |
Mike Jordan
|
|
|
MOved to PM
|
BLD-Conference | 6/4/2013 | 6/4/2013 | 6/4/2013 | P | DONE |
Mike Jordan
|
|
|
On site to check on job progress. Noted that lube center is erected and shop expansion is nearly 3/4 erected. Also noted that no inspections were scheduled. Did note that all work has been inspected by special inspection. Noted to contractor that he is still required to schedule inspections with the building dept. While on site walk through lube expansion and observed grout placement on shop expansion from 12ft to 16ft. elevation. Also reviewed all special inspection reports to date.
|
BLD-Footing | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | DEFR |
Mike Jordan
|
|
|
gary - pouring at 10:30 Phone #: ###-####. Mti on site.
|