Information based on query as of Tuesday, May 21, 2024.
Permit Information
Permit NumberBLD12-03333
StatusFinaled
Name CSDI CONSTRUCTION INC
Site Address 1357 N LILLY AVE
Project NameKeeneland Park
Customer Number 
ePlanReviewYes
Description
Keeneland Park Clubhouse - To construct a new 2,539 square foot, one story, wood framed, multi-purpose residential community clubhouse for the Keenland Park subdivision. The clubhouse will have a 1,067 sq.ft. Great room/Warming Kitchen/Dining area/Sitting room/ Entry lobby, two accessible restrooms, a 373 sq.ft. Exercise room, a 200 sq.ft. Managers office, a 221 sq.ft. leasing/Office, an attached 94 sq.ft. Covered porch, a attached 230 sq.ft. covered rear patio, an 124 sq.ft. Attached pool equipment storage room, and related site improvements. The occupant load for the clubhouse portion is 72 and shall be posted in a conspicuous place, near the main exit. This permit does not include the installation of the swimming pool. A separate permit is required to construct the swimming pool. All construction shall be per the approved plans, Engineering, approvals from all other reviewing departments, and the attached plan review report. This building is NOT fire sprinklered. DRH12-00344 - CUP05-00009 per Planning and Zoning. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/31/201310/31/201310/31/2013PPASS
DetailsMike Jordan
need final pass for perm occ since pw signed for perm. Ok for perm. occ
BLD-Final10/24/201310/25/201310/25/2013PPART
DetailsMike Jordan
PLease call Jeffrey 45 mins before site visit-Jeffrey Phone #: ###-####. Ok for temp occ. once public works signs temp. Will be ok for perm occ once public works signs perm.
BLD-Final9/17/20139/17/20139/17/2013PCANC
DetailsMike Jordan
rocko Phone #: ###-####. Cancelled by contractor via phone call.
BLD-Final9/10/20139/11/20139/11/2013ANR
DetailsJim Storey
rob Phone #: ###-#### open plm and mec permits need p&z sign off as well as public works
BLD-Conference9/4/20139/5/20139/5/2013ADONE
DetailsMike Jordan
Rocko Phone #: ###-####
FIRE-Final Inspection9/4/20139/4/20139/4/2013PPASS
DetailsTroy Cobbley
life safety passed. The sliding door hardware is not ADA compliant and will need to be corrected prior to the building final.
BLD-Framing/Rough-in6/27/20136/27/20136/27/2013PCANC
DetailsMike Jordan
rocco Phone #: ###-####
BLD-Energy code compliance6/27/20136/27/20136/27/2013PPASS
DetailsMike Jordan
rocco Phone #: ###-####
BLD-Framing/Rough-in6/25/20136/26/20136/25/2013APASS
DetailsJim Sly
Rocko Phone #: ###-####
BLD-Framing/Rough-in6/20/20136/20/20136/20/2013PFAIL
DetailsMike Jordan
rocco Phone #: ###-####. Complete airseal pack, fireblock all furdowns, provide truss engineering and strap beam to column connetctions.
FIRE-Conference6/18/20136/18/20136/19/2013PDONE
DetailsForrest France
On site conference regarding fire life safety conditions and requirements for occupancy approval.
BLD-Wall Bracing6/12/20136/12/20136/12/2013PPASS
DetailsMike Jordan
roco Phone #: ###-####
BLD-Wall Bracing6/11/20136/12/20136/12/2013AFAIL
DetailsMike Jordan
rocco Phone #: ###-####. Provide conversion chart or nail off per approved plan.
BLD-Foundation5/14/20135/15/20135/15/2013APASS
DetailsMike Jordan
Late morning - rocco Phone #: ###-####
BLD-Footing5/10/20135/13/20135/13/2013PPASS
DetailsMike Jordan
rocco early pm if possible Phone #: ###-####0. Perimeter footings and column pad footings for front entry ok. No special inspection on concrete. Desighn 2,500psi per engineer of record.