BLD-Final | 4/27/2015 | 4/27/2015 | 4/27/2015 | P | PASS |
Jim Storey
|
|
|
Cherry Phone #: ###-####
|
FIRE-Final Inspection | 4/24/2015 | 4/27/2015 | 4/27/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PART |
Forrest France
|
|
|
Fire life safety inspection at the new hangar completed acceptable.
|
BLD-Final | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PART |
Mike Jordan
|
|
|
for temp on hangar // Teri Phone #: ###-####. hangar ok, pending fire/life/safety.
|
BLD-Final | 10/3/2014 | 10/6/2014 | 10/6/2014 | A | PASS |
Jim Storey
|
|
|
Teri Phone #: ###-#### office ok boiller rm needs firestopped
|
FIRE-Final Inspection | 10/1/2014 | 10/1/2014 | 10/1/2014 | P | PART |
Troy Cobbley
|
|
|
Fire sprinkler, fire alarm and fire life safety complete in the new office area (basement, first & second floors). New office area only. The remaining new hanger area is not complete yet.
|
FIRE-Final Inspection | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | FAIL |
Troy Cobbley
|
|
|
To complete the life safety in the new office area only I need the fire alarm system corrections completed and all of the emergency lights and exit signs installed and functional.
|
FIRE-Final Inspection | 9/25/2014 | 9/25/2014 | 9/26/2014 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints.
|
BLD-Conference | 8/25/2014 | 8/26/2014 | 8/27/2014 | A | PASS |
Jim Storey
|
|
|
Terry Phone #: ###-####
|
BLD-Other | 7/17/2014 | 7/18/2014 | 7/18/2014 | A | PASS |
Jim Storey
|
|
|
Fire block on stairway - Terri Phone #: ###-#### fire stopping ok ok to instal hard lid
|
BLD-Conference | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | PASS |
Jim Storey
|
|
|
Terry Phone #: ###-####
|
BLD-Framing/Rough-in | 7/14/2014 | 7/15/2014 | 7/15/2014 | A | PART |
Jim Storey
|
|
|
partial framing on west side of hangar & acoustical ceiling grid insp in basement // Teri Phone #: ###-#### all hard ceillings and part of east drop ceillings ok/ need to fire stop west stair above hard lid.
|
BLD-Framing/Rough-in | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Jim Storey
|
|
|
Teri Phone #: ###-####
|
BLD-Framing/Rough-in | 5/9/2014 | 5/13/2014 | 5/13/2014 | A | PART |
Jim Storey
|
|
|
terri Phone #: ###-#### 2 hr exterior ok office framing ok pending review. and trade ri.
|
BLD-Conference | 4/8/2014 | 4/8/2014 | 4/8/2014 | P | FAIL |
Jim Storey
|
|
|
arch to provide to planreview east wall [ ie 2hr exterior wall ] details and listing not per the aproved plan. 5a-3.4 grid linec-2 thrur c6.
|
BLD-Conference | 4/4/2014 | 4/7/2014 | 4/7/2014 | P | PART |
Jim Storey
|
|
|
Skip Jones Phone #: ###-#### need to meet with plan review.
|
BLD-Framing/Rough-in | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | PASS |
Jim Storey
|
|
|
terri Phone #: ###-#### bathrm west bldg ok to cover/ vent fan ducted thru roof.
|
BLD-Framing/Rough-in | 3/13/2014 | 3/14/2014 | 3/14/2014 | A | FAIL |
Jim Storey
|
|
|
Teri Phone #: ###-#### duct in 2 hr wall no protection/ backing ada
|
BLD-Wall cover | 2/24/2014 | 2/25/2014 | 2/25/2014 | A | PASS |
Tom Arcoraci
|
|
|
Reinspection of fire wall in existing hangar, Also erection of stair systems has begun and open for review. Observation of hangar door rail system work in wip of 2 hr wall ok
|
BLD-Grading Inspection | 1/24/2014 | 1/27/2014 | 1/27/2014 | P | PART |
Jim Storey
|
|
|
Slab on grade base rock ready for insp. Planning spray on insulation/vapor barrier Tues. Also have MTI Density tests Monday afternoon. Phone #: ###-#### >> Inspection requested via web by Teri Kiser mti to verify.
|
BLD-Foundation | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | PART |
Jim Sly
|
|
|
Door rail lower foundation slab gridline 2. Please visit any time before 10am as concrete is scheduled for Noon. Thanks Phone #: ###-#### >> Inspection requested via web by Teri Kiser Door rail slab OK pending MTI special inspection, tests and approvals. MTI approval of soil bearing.
|
BLD-Foundation | 1/16/2014 | 1/17/2014 | 1/17/2014 | A | PASS |
Jim Storey
|
|
|
Please if possible visit by 9am, col. pedestal B/5 and small frost wall (less than 2 yds). Conc. pour @ 10am. Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Foundation | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | PASS |
Jim Storey
|
|
|
Prefer visit btw 10am & 11am, foundation pedestals @ B line, ftg B/5, walls 8 line, north ftg @ 2 line. Concrete scheduled for 1pm w/ MTI rebar insp and samples. Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Foundation | 1/10/2014 | 1/13/2014 | 1/13/2014 | A | PASS |
Jim Storey
|
|
|
Column pedestals & foundation walls line C, also ftgs line B. Prefer approx. visit btw 10am & 11am due to concrete pour set up for 1pm. As always MTI to insp rebar w/ conc. samples. Phone #: ###-#### >> Inspection requested via web by Teri Kiser engineer to adress changes with si insp.
|
BLD-Footing | 1/6/2014 | 1/7/2014 | 1/7/2014 | A | PASS |
Jim Storey
|
|
|
Btw 10am & 11Am preferred to insp ftgs, MTI insp due @ 12:30pm, concrete scheduled for 1pm... Also, steel deck puddle welding insp (which prev. passed insp by MTI) Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Wall cover | 12/26/2013 | 12/26/2013 | 12/26/2013 | P | PART |
Jim Storey
|
|
|
frmg @ mech rm, puddle welding L1 decking, grading existing pipe Hazwhopper ops per EPA Phone #: ###-#### >> Inspection requested via web by Teri Kiser / nr/ 2hr wall esisting building top of wall and ends to be extented.
|
BLD-Foundation | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Jim Storey
|
|
|
10:00 am pour time remaining bsmt wall MTI monitoring Cold weather concreting plan established Heaters, tenting etc... Phone #: ###-#### >> Inspection requested via web by Teri Kiser heat and protection in place/ si on site/ rebar ok to place concrete/ drainage protection aplied to exterior wall ok to start back fil.
|
BLD-Concrete | 11/27/2013 | 12/2/2013 | 12/2/2013 | P | PASS |
Jim Storey
|
|
|
SOG at basement Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Footing | 11/22/2013 | 11/25/2013 | 11/25/2013 | A | PASS |
Jim Storey
|
|
|
Ftg line 6 btw stairwell and elevator pit Should be ready for insp after 10am Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Foundation | 11/21/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Jim Storey
|
|
|
Bsmt walls line B and 6 Phone #: ###-#### >> Inspection requested via web by Teri Kiser west end 1/2 of northeast walls ok
|
BLD-Foundation | 11/20/2013 | 11/21/2013 | 11/21/2013 | P | CANC |
Jim Storey
|
|
|
Basement walls lines B and 6 MTI to follow with SI prior to pour Phone #: ###-#### >> Inspection requested via web by Teri Kiser Inspection cancelled from web by: Teri Kiser
|
BLD-Concrete | 11/13/2013 | 11/14/2013 | 11/14/2013 | P | PASS |
Jim Storey
|
|
|
Walls on south and east end of basement Phone #: ###-#### >> Inspection requested via web by Teri Kiser ft north side 1/2 east to west/ wall ok pending si reports.
|
BLD-Footing | 11/6/2013 | 11/7/2013 | 11/7/2013 | P | PART |
Jim Storey
|
|
|
Includes elev pit walls Phone #: ###-#### >> Inspection requested via web by Teri Kiser west ft ok pending si
|
BLD-Footing | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | PART |
Jim Storey
|
|
|
MARK Phone #: ###-#### si ok east end ft ok.
|