BLD-Final | 10/24/2014 | 10/27/2014 | 10/27/2014 | P | PASS |
Jim Sly
|
|
|
Brandon Phone #: ###-####
|
FIRE-Final Inspection | 10/24/2014 | 10/27/2014 | 10/27/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 10/20/2014 | 10/21/2014 | 10/21/2014 | P | NR |
Forrest France
|
|
|
Incompleted C/N items. Exit discharge lighting not yet installed.
|
BLD-Conference | 8/5/2014 | 8/5/2014 | 8/5/2014 | P | DONE |
Jim Sly
|
|
|
Received TCO sign off from zoning/landscape. Looking for structural TCO. Hired new sider. Hired new landscaper. Roofer working and awaiting upper siding. Phone #: ###-#### Inspection requested via web by Brandon Juarez
|
BLD-Final | 8/5/2014 | 8/5/2014 | 8/5/2014 | P | PART |
Jim Sly
|
|
|
OK for Temp Occ. OK for Perm Occ. when Roofing, Siding, is done. Fire, and zoning is finaled.
|
BLD-Final | 7/29/2014 | 7/29/2014 | 7/29/2014 | P | NR |
Jim Sly
|
|
|
Requesting a TCO meeting. client needs to start moving in. Sider quit and roofer quit. need your help. Phone #: ###-#### Inspection requested via web by Brandon Juarez Brandon to obtain Occ request card and complete req finals.
|
FIRE-Final Inspection | 7/29/2014 | 7/29/2014 | 7/29/2014 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given, with scott arellano's permission, until the correct exit discharge lights have been ordered, installed and tested.
|
FIRE-Final Inspection | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | FAIL |
Troy Cobbley
|
|
|
Repair exit signs, provide indicator on the main exit door. Provide fire extinguisher on the upper level. Provide listed for the enviroment exit discharge lights. Provide building address
|
FIRE-Final Inspection | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | FAIL |
Craig D. Hanson
|
|
|
Need emergency lighting and exit signs to illuminate. Hardware needs installed on back door. breaker box needs cover and labeles. outlets need covers. Extinguisher to be mounted in back hall.
|
BLD-Energy code compliance | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | PASS |
Mike Jordan
|
|
|
brandon Phone #: ###-####
|
BLD-Framing/Rough-in | 6/11/2014 | 6/11/2014 | 6/11/2014 | P | PASS |
Jim Sly
|
|
|
brandon - ###-####
|
BLD-Energy code compliance | 6/10/2014 | 6/10/2014 | 6/10/2014 | P | NR |
Jim Sly
|
|
|
Electrical inspection AM. Then cover shear panels for PM framing and energy inspection Phone #: ###-#### >> Inspection requested via web by Brandon Juarez
|
BLD-Framing/Rough-in | 6/10/2014 | 6/10/2014 | 6/10/2014 | P | PEND |
Jim Sly
|
|
|
Electrical inspection AM. Then cover shear panels for PM framing and energy inspection Phone #: ###-#### >> Inspection requested via web by Brandon Juarez Walk thru.....
|
BLD-Wall Bracing | 5/1/2014 | 5/1/2014 | 5/1/2014 | P | PASS |
Jim Sly
|
|
|
EARLY PM OK. We need a sheer inspection so we can cover some sections of the building. we also want to install Tyvek over the exterior sheer. talk to KENT on site thanks - Brandon ###-#### Phone #: ###-#### >> Inspection requested via web by Brandon Juarez
|
BLD-Foundation | 2/24/2014 | 2/25/2014 | 2/25/2014 | A | PASS |
Jim Sly
|
|
|
FOUNDATION WALL INSPECTION ON BUILDING Phone #: ###-#### >> Inspection requested via web by Brandon Juarez
|
BLD-Footing | 2/18/2014 | 2/19/2014 | 2/19/2014 | P | PASS |
Jim Sly
|
|
|
Late AM or Early PM requested Concrete expected at 1:30 pm Phone #: ###-#### >> Inspection requested via web by Brandon Juarez
|