Permit Information
Permit NumberBLD14-00484
StatusFinaled
Name EMBREE CONSTRUCTION GROUP INC
Site Address 291 N MILWAUKEE ST
Project NameEyemart Express
Customer Number 
ePlanReviewNo
Description
(EYEMART EXPRESS – Westgate Towne Plaza - Expansion) This permit is to expand a 2,785 square foot existing tenant space (Eyemart – BLD95-02139) into the adjacent 1,500 square foot tenant space (Cricket – BLD01-01651) to create a new 4,458 square foot mercantile / office tenant space. This building is sprinklered for area increase. Work is to include: new plumbing, demolition of interior non-bearing walls, new electrical, new mechanical, new accessible doors / hardware, and interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/1/20147/1/20147/1/2014PPASS
DetailsMike Jordan
or ###-#### Scott Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection7/1/20147/1/20147/1/2014PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection6/23/20146/23/20146/23/2014PPART
DetailsTroy Cobbley
Life safety in phase 2 and 3 passed.
BLD-Framing/Rough-in6/12/20146/13/20146/13/2014PPASS
DetailsMike Jordan
Ceiling cover inspection-Scott Phone #: ###-####
BLD-Framing/Rough-in6/5/20146/5/20146/5/2014PPASS
DetailsMike Jordan
Scott Phone #: ###-####. Interior steel stud walls only ok, phase 2.
BLD-Final5/15/20145/16/20145/16/2014APART
DetailsMike Jordan
. ok to occupy east portion of tje tenant improvement while the existing portion is being remodeled.
FIRE-Final Inspection5/15/20145/16/20145/16/2014APART
DetailsTroy Cobbley
See the city approved plans for Phase I location where life safety is complete. Panic hardware is to be installed on front door per the door schedule prior to final sign off of whole project. Scott #: ###-####
BLD-Final5/15/20145/15/20145/15/2014PNR
DetailsMike Jordan
FIRE-Final Inspection5/14/20145/15/20145/15/2014ACANC
DetailsTroy Cobbley
Cancel per scott Phone #: ###-####
BLD-Final5/14/20145/15/20145/15/2014ACANC
DetailsMike Jordan
scott Phone #: ###-####. Moved to pm.
FIRE-Conference5/14/20145/14/20145/14/2014PDONE
DetailsTroy Cobbley
Went over life safety requirements with Scott. I agreed that since the doors are not here yet if case work was installed I would be ok with a pass on life safety in this phase of work.
BLD-Final5/13/20145/14/20145/14/2014PCANC
DetailsMike Jordan
Scott Phone #: ###-####
BLD-Ceiling Grid Inspection5/14/20145/14/20145/14/2014PPASS
DetailsMike Jordan
Scott Phone #: ###-####
BLD-Framing/Rough-in4/24/20144/25/20144/25/2014PPASS
DetailsMike Jordan
scott Phone #: ###-####. Interior steel stud walls, no grid at phase 1 (1500s.f. addition into adjacent tenant space).