BLD-Final | 9/8/2015 | 9/9/2015 | 9/9/2015 | P | PASS |
Jim Sly
|
|
|
Jerrod Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 9/8/2015 | 9/9/2015 | 9/9/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Conference | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | DONE |
Troy Cobbley
|
|
|
discussed exit sign locations
|
BLD-Framing/Rough-in | 8/7/2015 | 8/10/2015 | 8/10/2015 | A | PASS |
Mike Jordan
|
|
|
Jared Phone #: ###-####. INterior steel stud framed walls ok.
|
BLD-Final | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PART |
Mike Jordan
|
|
|
Please call 1/2 hr before inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner. Ok for temp occ.
|
FIRE-Final Inspection | 4/28/2015 | 4/28/2015 | 4/29/2015 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is given until this building permit and the associated fire sprinkler permit has been resubmitted for a plan modification showing the new de-mountable wall arrangement. At this time life safety is passed and fire sprinkler coverage is ok.
|
BLD-Framing/Rough-in | 4/7/2015 | 4/8/2015 | 4/8/2015 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner. Interior steel stud framed walls for new breakroom, door infill, and IT/server room.
|
BLD-Conference | 4/6/2015 | 4/6/2015 | 4/6/2015 | P | DONE |
Mike Jordan
|
|
|
To discuss requirements for TCO. Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Conference | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | DONE |
Jim Sly
|
|
|
To discuss parameters for TCO Phone #: ###-#### Inspection requested via web by Jared Waggoner
|