FIRE-Final Inspection | 1/4/2018 | 1/5/2018 | 1/5/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection complete.
|
FIRE-Final Inspection | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | FAIL |
Jim Page
|
|
|
Modifications required for audio/visual devices on fire alarm system in apartment restrooms that are ADA compliant, when fire alarm modifications are complete then permit can be finaled for life fire safety.
|
BLD-Final | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Jim Sly
|
|
|
Ed Phone #: ###-#### Structural final.......OK.
|
BLD-Final | 1/3/2018 | 1/3/2018 | 1/3/2018 | P | NR |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Energy code compliance | 10/23/2017 | 10/24/2017 | 10/24/2017 | A | PASS |
Tony Young
|
|
|
1st floor // Ed Phone #: ###-####,, ok pending trades
|
BLD-Wall cover | 10/23/2017 | 10/23/2017 | 10/24/2017 | P | PART |
Tony Young
|
|
|
1st floor // Ed Phone #: ###-####
|
BLD-Conference | 10/20/2017 | 10/20/2017 | 10/21/2017 | P | DONE |
Tony Young
|
|
|
1st floor Fire Clucking- ED Phone #: ###-####
|
BLD-Framing/Rough-in | 10/19/2017 | 10/19/2017 | 10/20/2017 | P | PASS |
Tony Young
|
|
|
1st floor- ED Phone #: ###-####
|
BLD-Other | 10/19/2017 | 10/19/2017 | 10/20/2017 | P | PART |
Tony Young
|
|
|
1st floor Fire Clucking- ED Phone #: ###-####,,, needs to fix a couple spot
|
BLD-Energy code compliance | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | PASS |
Mike Jordan
|
|
|
Ed Phone #: ###-####. 2nd. floor, eight units ok.
|
BLD-Other | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | PART |
Jim Sly
|
|
|
Ed-fire caulking Phone #: ###-#### 8 Units
|
BLD-Framing/Rough-in | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | PART |
Jim Sly
|
|
|
Ed Phone #: ###-#### 8 units
|
BLD-Energy code compliance | 9/6/2017 | 9/7/2017 | 9/8/2017 | P | PASS |
Tony Young
|
|
|
3rd floor... insulation // Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | PASS |
Tony Young
|
|
|
3rd floor // Ed Phone #: ###-####
|
BLD-Other | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | PASS |
Tony Young
|
|
|
3rd floor... fire colcking // Ed Phone #: ###-####
|
BLD-Energy code compliance | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | PART |
Tony Young
|
|
|
3rd floor... insulation // Ed Phone #: ###-####,, south side units ok
|
BLD-Framing/Rough-in | 8/25/2017 | 8/28/2017 | 8/28/2017 | A | PART |
Tony Young
|
|
|
Floors 1 and 2 // Ed Phone #: ###-####,, prerock areas ok
|
BLD-Energy code compliance | 8/24/2017 | 8/25/2017 | 8/25/2017 | P | NR |
Tony Young
|
|
|
Floors 1 and 2 // Ed Phone #: ###-####
|
BLD-Energy code compliance | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PART |
Tony Young
|
|
|
3rd floor // Ed Phone #: ###-####,, ceiling pre-rock ok
|
BLD-Framing/Rough-in | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PART |
Brandon Shaw
|
|
|
Framing and fire caulkings on 1st floor OK to insulate
|
BLD-Other | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PART |
Brandon Shaw
|
|
|
Framing and fire caulkings on 1st floor
|
BLD-Framing/Rough-in | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | PASS |
Jim Sly
|
|
|
barry-framing and fire caulk-2nd and 3rd floor Phone #: ###-####
|
BLD-Framing/Rough-in | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PART |
Tony Young
|
|
|
Berry Phone #: ###-#### ,, insulation behind tubs/shower areas ok after fireblocking plate lines
|
BLD-Energy code compliance | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Tony Young
|
|
|
Ed 4th floor insulation Phone #: ###-####
|
BLD-Energy code compliance | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | NR |
Tony Young
|
|
|
Ed 4th floor insulation Phone #: ###-####,, needs sprinkler passed 1st
|
BLD-Energy code compliance | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | NR |
Tony Young
|
|
|
Ed Phone #: ###-####, 4th floor
|
BLD-Framing/Rough-in | 8/11/2017 | 8/11/2017 | 8/12/2017 | P | DEFR |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Other | 8/11/2017 | 8/11/2017 | 8/12/2017 | P | DEFR |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Wall Bracing | 7/31/2017 | 7/31/2017 | 8/1/2017 | P | PASS |
Tony Young
|
|
|
Elevator shear // Ed Phone #: ###-####
|
BLD-Energy code compliance | 6/8/2017 | 6/8/2017 | 6/9/2017 | P | PASS |
Tony Young
|
|
|
Ed-plumbing wall insulation Phone #: ###-####
|
BLD-Wall Bracing | 6/2/2017 | 6/5/2017 | 6/5/2017 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, sill plates on interior for pre rock
|
BLD-Wall Bracing | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PART |
Tony Young
|
|
|
exterior shear - Ed Phone #: ###-####, exterior only,, not breeze ways, work in progress,, ok after re-doing some areas
|
BLD-Footing | 12/29/2016 | 12/30/2016 | 12/30/2016 | A | PART |
Jim Storey
|
|
|
Ed Phone #: ###-#### ok w si
|
BLD-Footing | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####, slab work,, ok pending trades,, special inspection results,, cold weather provisions in effect
|
BLD-Footing | 12/20/2016 | 12/21/2016 | 12/21/2016 | A | PEND |
Tony Young
|
|
|
Ed Phone #: ###-####,, special inspection
|
BLD-Footing | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | PASS |
Jim Sly
|
|
|
Ed Phone #: ###-#### OK pending Geotech special inspections, tests and approvals.
|
BLD-Footing | 10/13/2016 | 10/14/2016 | 10/14/2016 | A | PEND |
Tony Young
|
|
|
Ed Phone #: ###-####,, special inspection reports
|