Permit Information
Permit NumberBLD15-02932
StatusFinaled
Name MJB & ASSOCIATES LLC
Site Address 3013 E WINDSONG DR
Project Name3013 Windsong
Customer Number 
ePlanReviewYes
Description
WUI Zone A; Permit for the construction of a new 4,864 sq. ft., one story with a basement level (main story 2,807 sq. ft., basement level 2,057 sq. ft.) single family dwelling with 5 bedrooms, 4 & 1/2 bathrooms, approximately 855 sq. ft. of covered patio/porch and a 1,465 sq. ft. attached garage per the approved plans, engineering, ACCA report and any notations. R-1A/DA zoning and setbacks per planning.//leg ***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/22/20191/23/20191/23/2019APASS
DetailsBrandon Shaw
Sam Phone #: ###-####
DOC - Permit Finaled1/23/20191/23/20191/23/2019PPASS
DetailsBrandon Shaw
BLD-Final1/17/20191/18/20191/18/2019ANR
DetailsBrandon Shaw
Need PW to approve the roof storm drainage system...
BLD-Aging Inspection1/18/20191/18/20191/18/2019 CANC
DetailsBrandon Shaw
BLD-Aging Inspection1/17/20191/17/20191/17/2019 DEFR
DetailsBrandon Shaw
Work in progress...
BLD-Other9/26/20189/26/20189/26/2018PPASS
DetailsBrandon Shaw
sofit- Sam Phone #: ###-####
BLD-Other9/21/20189/21/20189/21/2018PCANC
DetailsBrandon Shaw
Cancel per Sam softits- Sam Phone #: ###-####
BLD-Other9/17/20189/17/20189/17/2018PPART
DetailsBrandon Shaw
Work in progress...
Under deck and covered deck area
BLD-Energy code compliance9/5/20189/5/20189/5/2018PPASS
DetailsBrandon Shaw
OK to cover
BLD-Energy code compliance8/31/20188/31/20188/31/2018PPASS
DetailsBrandon Shaw
BLD-Framing/Rough-in8/31/20188/31/20188/31/2018PPASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in8/27/20188/28/20188/28/2018PPASS
DetailsBrandon Shaw
Shear corrections SAT...
As per walk thu...
Add straps at breaks in double top plates
Tripple ply grider to bear down to foundation
See red paint
OK to insulate
BLD-Framing/Rough-in8/17/20188/21/20188/21/2018AFAIL
DetailsBrandon Shaw
Address to be visible form the street...
Need trades rough in approvals...
No air/foam seal...
Wall bracing failed
a) Hold down and straps to be as per plans
b) Per S1.1, details 5 & 6, 2x6 walls to be 16" O.C.
c) Anchor bolts to be not more than 12" from ends of sill plates
See red paint
BLD-Conference3/21/20183/21/20183/21/2018APEND
DetailsBob Archibald
Recieved request for permit reactivation. Permit may be reactivated for 1/2 of original fee (only footings inspections have been completed).
BLD-Aging Inspection5/25/20165/25/20165/25/2016 PEND
DetailsPhil Shearer
BLD-Aging Inspection5/24/20165/24/20165/24/2016 PEND
DetailsPhil Shearer
BLD-Foundation1/11/20161/11/20161/11/2016PPASS
DetailsPhil Shearer
J.R. Phone #: ###-####
BLD-Foundation12/23/201512/24/201512/24/2015APASS
DetailsPhil Shearer
J.R. Phone #: ###-####
BLD-Footing12/11/201512/14/201512/14/2015PPART
DetailsTony Young
J.R. Phone #: ###-####,, crawl area,, work in progress,, will pour 12/15,, will blanket forms tonight
BLD-Foundation12/2/201512/3/201512/3/2015APASS
DetailsPhil Shearer
JR Phone #: ###-####
BLD-Foundation12/1/201512/2/201512/2/2015PCANC
DetailsPhil Shearer
FIrst thing PM please, would like to pour @ 2 - JR Phone #: ###-####
BLD-Footing11/20/201511/20/201511/20/2015PPASS
DetailsPhil Shearer
BLD-Footing11/19/201511/19/201511/19/2015PNR
DetailsPhil Shearer
Pouring at 1 - JR Phone #: ###-####
BLD-Footing11/18/201511/19/201511/19/2015ACANC
DetailsPhil Shearer
Pouring at 1 - JR Phone #: ###-####
BLD-Footing11/18/201511/18/201511/18/2015PCANC
DetailsPhil Shearer
Pouring at 3 - JR Phone #: ###-####
BLD-Footing11/17/201511/18/201511/18/2015ACANC
DetailsPhil Shearer
Pouring at 3 - JR Phone #: ###-####
BLD-Foundation11/17/201511/17/201511/17/2015PPASS
DetailsPhil Shearer
Pouring at 3 - JR Phone #: ###-####
BLD-Footing11/4/201511/5/201511/6/2015PPART
DetailsPhil Shearer
JR Phone #: ###-####-- pour time is 330 Basement only