BLD-Final | 11/17/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Jim Sly
|
|
|
OK for Perm Occ. when all Requirements for Perm Occ. are met.
|
BLD-Aging Inspection | 11/10/2017 | 11/10/2017 | 11/17/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 8/21/2017 | 8/21/2017 | 8/28/2017 | | CANC |
Jim Sly
|
|
|
|
BLD-Final | 6/2/2017 | 6/2/2017 | 6/2/2017 | P | PART |
Jim Sly
|
|
|
OK for Temp Occ. OK for Perm Occ. when all required trades and agencies on signature card signs for Perm. Occ.
|
FIRE-Final Inspection | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 5/30/2017 | 5/31/2017 | 5/31/2017 | P | NR |
Jim Sly
|
|
|
Roger Phone #: ###-#### Need all required finals.
|
BLD-Ceiling Grid Inspection | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Jim Sly
|
|
|
fire caulking; Roger Phone #: ###-####
|
BLD-Other | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Jim Sly
|
|
|
fire caulking; Roger Phone #: ###-####
|
BLD-Other | 2/7/2017 | 2/8/2017 | 2/8/2017 | A | PASS |
Mike Jordan
|
|
|
Dave//Fire caulking Phone #: ###-####. firecaulking at 2nd floor mech. shaft ok to rcock.
|
BLD-Conference | 12/30/2016 | 1/3/2017 | 1/3/2017 | A | PASS |
Jim Sly
|
|
|
Part of the first and second floor // Dave Phone #: ###-#### All Framing Approved.....Pending all trade rough ins approved.
|
BLD-Framing/Rough-in | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Dorm Rooms OK.
|
BLD-Framing/Rough-in | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Front....Exterior wall framing...OK.
|
BLD-Wall Bracing | 11/4/2016 | 11/7/2016 | 11/8/2016 | P | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### No bracing to look at yet, but OK to cover East, South and West exterior wall on the outside.
|
BLD-Other | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | PASS |
Jim Sly
|
|
|
rebar/slab - Dave Phone #: ###-#### OK pending STRATA special insp, tests and approvals.
|
BLD-Foundation | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | PASS |
Jim Sly
|
|
|
Dave-re-enforcing-grouting CMU Block Phone #: ###-####
|
BLD-Other | 8/25/2016 | 8/26/2016 | 8/26/2016 | P | DONE |
Jim Sly
|
|
|
Dave-reinforcing grout-times 2:00 Phone #: ###-#### STRATA on site.
|
BLD-Other | 8/25/2016 | 8/26/2016 | 8/26/2016 | A | PART |
Jim Sly
|
|
|
Dave-reinforcing grout-times 9:30 Phone #: ###-#### Select CMU reinforcement/grout OK pending STRATA special inspections, tests and approvals.
|
BLD-Foundation | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Select walls....OK pending STRATA special inspections, tests and approvals.
|
BLD-Foundation | 8/18/2016 | 8/19/2016 | 8/19/2016 | P | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### STRATA on site.
|
BLD-Concrete | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### CMU grout pour select walls OK pending STRATA special inspections, tests and approvals.
|
BLD-Concrete | 8/15/2016 | 8/16/2016 | 8/16/2016 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### CMU grout pour......2nd lift, select walls OK pending STRATA special inspections, tests and approvals.
|
BLD-Other | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | PART |
Jim Sly
|
|
|
Dave ###-#### grout inspection Phone #: ###-#### 1st pour......OK pending SRATA special inspections,tests and approvals.
|
FIRE-Conference | 7/13/2016 | 7/14/2016 | 7/13/2016 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was just for the stub out from the building. Top of pipe measured 4'-2" to the top of the footing. Per the job superintendant and the underground installer an additional 12" of dirt is to be installed on top of the pipe. This will give the required 4'-6" of cover.
|
BLD-Footing | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PART |
Jim Sly
|
|
|
Dusty Phone #: ###-#### Select Footings OK pending STRATA special insp, tests and approvals.
|