Permit Information
Permit NumberBLD16-01040
StatusFinaled
Name ESI
Site Address 8485 W USTICK RD
Project NameBoise Fire Station 4
Customer NumberBLD16-01035 DEMO
ePlanReviewYes
Description
**Project Management-Ron Hill** **GREEN TAG EXPEDITED REVIEW - Review to 2012 IgCC** (CITY OF BOISE - Fire Station #4) Permit to construct a new 13,774 square foot fire station. This building is fire sprinklered for area increase and non-separated uses. This building utilizes enhanced lighting to comply with the 2012 IECC / IgCC. Scope of work includes: construction of poured concrete foundation, construction of reinforced CMU exterior walls, construction of new steel bar-joist floor – ceiling framing / steel pan deck, [construction of interior nonbearing walls to create: 10 sleeping units, 8 restrooms / bathing rooms, lobby, two offices, work room, turn out room, decon room, maintenance shop, riser room, SCBA Fill room, 3 storage rooms, laundry room, janitors closet, training classroom, fitness room, and dayroom], new elevator, new electrical, new plumbing, new mechanical, new interior / exterior finishes, new accessible doors / hardware, covered patio on 2nd floor, and related site work. This building is fully fire sprinklered for area increase. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/17/201711/17/201711/17/2017APASS
DetailsJim Sly
OK for Perm Occ. when all Requirements for Perm Occ. are met.
BLD-Aging Inspection11/10/201711/10/201711/17/2017 CANC
DetailsJim Sly
BLD-Aging Inspection8/21/20178/21/20178/28/2017 CANC
DetailsJim Sly
BLD-Final6/2/20176/2/20176/2/2017PPART
DetailsJim Sly
OK for Temp Occ. OK for Perm Occ. when all required trades and agencies on signature card signs for Perm. Occ.
FIRE-Final Inspection5/31/20176/1/20176/1/2017APASS
DetailsTroy Cobbley
life safety passed
BLD-Final5/30/20175/31/20175/31/2017PNR
DetailsJim Sly
Roger Phone #: ###-####
Need all required finals.
BLD-Ceiling Grid Inspection4/4/20174/4/20174/4/2017PPASS
DetailsJim Sly
fire caulking; Roger Phone #: ###-####
BLD-Other4/4/20174/4/20174/4/2017PPASS
DetailsJim Sly
fire caulking; Roger Phone #: ###-####
BLD-Other2/7/20172/8/20172/8/2017APASS
DetailsMike Jordan
Dave//Fire caulking Phone #: ###-####. firecaulking at 2nd floor mech. shaft ok to rcock.
BLD-Conference12/30/20161/3/20171/3/2017APASS
DetailsJim Sly
Part of the first and second floor // Dave Phone #: ###-####
All Framing Approved.....Pending all trade rough ins approved.
BLD-Framing/Rough-in12/13/201612/14/201612/14/2016APART
DetailsJim Sly
Dave Phone #: ###-####
Dorm Rooms OK.
BLD-Framing/Rough-in11/17/201611/18/201611/18/2016APART
DetailsJim Sly
Phone #: ###-####
Front....Exterior wall framing...OK.
BLD-Wall Bracing11/4/201611/7/201611/8/2016PPART
DetailsJim Sly
Dave Phone #: ###-####
No bracing to look at yet, but OK to cover East, South and West exterior wall on the outside.
BLD-Other10/6/201610/7/201610/7/2016APASS
DetailsJim Sly
rebar/slab - Dave Phone #: ###-####
OK pending STRATA special insp, tests and approvals.
BLD-Foundation8/29/20168/30/20168/30/2016APASS
DetailsJim Sly
Dave-re-enforcing-grouting CMU Block Phone #: ###-####
BLD-Other8/25/20168/26/20168/26/2016PDONE
DetailsJim Sly
Dave-reinforcing grout-times 2:00 Phone #: ###-####
STRATA on site.
BLD-Other8/25/20168/26/20168/26/2016APART
DetailsJim Sly
Dave-reinforcing grout-times 9:30 Phone #: ###-####
Select CMU reinforcement/grout OK pending STRATA special inspections, tests and approvals.
BLD-Foundation8/23/20168/24/20168/24/2016APART
DetailsJim Sly
Dave Phone #: ###-####
Select walls....OK pending STRATA special inspections, tests and approvals.
BLD-Foundation8/18/20168/19/20168/19/2016PPART
DetailsJim Sly
Dave Phone #: ###-####
STRATA on site.
BLD-Concrete8/17/20168/18/20168/18/2016APART
DetailsJim Sly
Dave Phone #: ###-####
CMU grout pour select walls OK pending STRATA special inspections, tests and approvals.
BLD-Concrete8/15/20168/16/20168/16/2016APART
DetailsJim Sly
Dave Phone #: ###-####
CMU grout pour......2nd lift, select walls OK pending STRATA special inspections, tests and approvals.
BLD-Other8/12/20168/12/20168/12/2016PPART
DetailsJim Sly
Dave ###-#### grout inspection Phone #: ###-####
1st pour......OK pending SRATA special inspections,tests and approvals.
FIRE-Conference7/13/20167/14/20167/13/2016ADONE
DetailsTroy Cobbley
Todays inspection was just for the stub out from the building. Top of pipe measured 4'-2" to the top of the footing. Per the job superintendant and the underground installer an additional 12" of dirt is to be installed on top of the pipe. This will give the required 4'-6" of cover.
BLD-Footing6/21/20166/21/20166/21/2016PPART
DetailsJim Sly
Dusty Phone #: ###-####
Select Footings OK pending STRATA special insp, tests and approvals.