Information based on query as of Thursday, May 16, 2024.
Permit Information
Permit NumberBLD16-02245
StatusFinaled
Name PETRA INC
Site Address 3135 E BARBER VALLEY DR
Project NameBoise Dance Alliance
Customer Number 
ePlanReviewYes
Description
(BOISE DANCE ALLIANCE) Permit to construct a new 5,700 square foot dance studio building. This building is not fire sprinklered and complies with ANSI / ASHREA 90.1. Scope of work includes: construction of poured concrete foundation, construction of wood framed exterior walls, construction of new wood truss roof framing, [construction of interior nonbearing walls to create: three studio spaces, a storage room, a lobby, an office, a reception area, a mechanical room, a family assist restroom / changing room, and a women’s restroom / dressing room], new electrical, new plumbing, new mechanical, new interior / exterior finishes, new accessible doors / hardware, new non-combustible awnings, and related site work. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/26/20177/26/20177/26/2017PPASS
DetailsBrandon Shaw
correct remote annunciators should be installed by noon. FLS called in.
Andy should have ESC finaled, and Pictures of trash gates are sent to Katelyn. Phone #: ###-#### Inspection requested via web by J.C. Murray
DOC - Permit Finaled7/26/20177/26/20177/26/2017PPASS
DetailsBrandon Shaw
FIRE-Final Inspection7/26/20177/26/20177/26/2017PPASS
DetailsJim Page
Previously noted items have been repaired. No fire sprinklers, only fire alarms are in-duct detection with stand alone annunciators (not monitored), fire extinguishers are in place with current inspection tags. Final life fire safey inspection passed/complete.
BLD-Final7/24/20177/25/20177/24/2017ACANC
DetailsBrandon Shaw
Phone #: ###-#### >> Inspection requested via web by J.C. Murray Inspection cancelled from web by: J.C. Murray
FIRE-Final Inspection7/24/20177/24/20177/24/2017PFAIL
DetailsTroy Cobbley
remote annunciators are not the correct ones. No testing performed.
FIRE-Final Inspection7/21/20177/21/20177/21/2017ACANC
DetailsTroy Cobbley
request 11am inspection. remote annunciators should be delivered, installed and functional by 11am. Phone #: ###-#### >> Inspection requested via web by J.C. Murray Inspection cancelled from web by: J.C. Murray
BLD-Final7/19/20177/20/20177/20/2017ANR
DetailsBrandon Shaw
mid morning OK. Phone #: ###-#### Inspection requested via web by J.C. Murray
FIRE-Final Inspection7/19/20177/19/20177/19/2017PFAIL
DetailsTroy Cobbley
FD vehicle access is approved for building "B" only with two available fire hydrants. The second required hydrant will be accessed from east Barber Valley Dr. until the parking lots have been completed servicing future buildings "A & C". *SJA*

For life safety to be finaled remote annunciators are required for the two duct smoke detectors and testing of the detectors.
BLD-Framing/Rough-in6/15/20176/15/20176/15/2017PPASS
DetailsBrandon Shaw
electrical cover scheduled for this afternoon Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance6/15/20176/15/20176/15/2017PPASS
DetailsBrandon Shaw
remaining exterior walls Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance6/13/20176/13/20176/13/2017PPART
DetailsBrandon Shaw
exterior walls Phone #: ###-#### Inspection requested via web by J.C. Murray
Studios 1, 2, & 3- exterior walls only
BLD-Conference6/7/20176/7/20176/7/2017PDONE
DetailsBrandon Shaw
Pre-framing inspection.
No issues, pending other trades rough in.
BLD-Framing/Rough-in6/7/20176/7/20176/7/2017PCANC
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Wall Bracing5/11/20175/12/20175/12/2017PPASS
DetailsBrandon Shaw
JC Phone #: ###-####
BLD-Foundation4/10/20174/10/20174/10/2017PPASS
DetailsJim Storey
Rebar // Paul Phone #: ###-####
BLD-Footing4/5/20174/6/20174/6/2017PPART
DetailsJim Storey
mud is scheduled at 3pm
Strata will be on site for rebar and concrete test. Phone #: ###-#### Inspection requested via web by J.C. Murray placed w si report to bshaw