BLD-Final | 7/31/2020 | 7/31/2020 | 8/3/2020 | P | PASS |
Jim Storey
|
|
|
Dillan *screened* Phone #: ###-####
|
FIRE-Final Inspection | 7/29/2020 | 7/31/2020 | 7/31/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspections are complete, fire alarm inspection is complete, fire extinguishers are placed throughout with current inspection tags. Final life fire safety inspection is complete, signatures provided on permit sign off card.
screened // Dillon Phone #: ###-####
|
FIRE-Conference | 6/16/2020 | 6/18/2020 | 6/18/2020 | A | DONE |
Jim Page
|
|
|
Fire conference complete, notated items for life fire safety.
Phone #: ###-#### Inspection requested via web by Dillon Barresi
|
FIRE-Alarm Testing | 4/21/2020 | 4/23/2020 | 4/23/2020 | A | DONE |
Jim Page
|
|
|
Fire alarm testing notes have been entered under permit FIR17-00178.
Fire Alarm Inspection for Micron Building 51. Phone #: ###-#### Inspection requested via web by Dillon Barresi
|
FIRE-Final Inspection | 10/11/2019 | 10/14/2019 | 10/14/2019 | P | CANC |
Jim Page
|
|
|
Inspection request for fire alarms needs to be completed under the associated FIR permit, no the BLD permit. Per conversation with the point of contact listed this request is cancelled and the correct permit for the fire alarms will need to be requested for fire alarm inspections.
For Fire Alarm Final Phone #: ###-#### Inspection requested via web by Dillon Barresi
|
FIRE-Final Inspection | 10/11/2019 | 10/15/2019 | 10/14/2019 | A | CANC |
Jim Page
|
|
|
For Fire Alarm Final Phone #: ###-#### >> Inspection requested via web by Dillon Barresi Inspection cancelled from web by: Dillon Barresi
|
BLD-Conference | 4/3/2019 | 4/3/2019 | 4/3/2019 | A | PEND |
Jim Storey
|
|
|
Expires: 05/23/18
|
BLD-Other | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PASS |
Jim Storey
|
|
|
Fire caulk inspection with Greg Phone #: ###-#### Inspection requested via web by Joel Hartman exterior penatrations glycol/ north west of 51/south west 50 exterior only ok to cover.
|
BLD-Other | 12/13/2017 | 12/13/2017 | 12/14/2017 | P | DEFR |
Jim Storey
|
|
|
Fire caulking. Greg Baisch Phone #: ###-#### Inspection requested via web by Joel Hartmanout of time
|
BLD-Other | 12/13/2017 | 12/14/2017 | 12/14/2017 | A | PART |
Jim Storey
|
|
|
Fire caulking. Greg Baisch Phone #: ###-#### Inspection requested via web by Joel Hartman firestopping outstanding areas on file w/greg
|
BLD-Other | 12/1/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Jim Storey
|
|
|
Greg Baisch, Fire caulking Phone #: ###-#### Inspection requested via web by Joel Hartman level 20 51 north/east res and other piping ok to cover
|
BLD-Other | 11/28/2017 | 11/28/2017 | 11/28/2017 | P | FAIL |
Jim Storey
|
|
|
Fire caulking with Greg Baisch Phone #: ###-#### Inspection requested via web by Joel Hartman 50 need minrial wool/1/2 min// 51 exterior wire band exterior ok
|
BLD-Aging Inspection | 11/23/2017 | 11/23/2017 | 11/24/2017 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 11/22/2017 | 11/22/2017 | 11/24/2017 | | PASS |
Jim Storey
|
|
|
|
BLD-Other | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | NR |
Jim Storey
|
|
|
Greg Baisch NE Pipe penetrations at Level 40. Phone #: ###-#### Inspection requested via web by Joel Hartman north side nr/ genral walk thru
|
BLD-Other | 11/6/2017 | 11/6/2017 | 11/6/2017 | P | PART |
Jim Storey
|
|
|
Greg Baisch Penetrations through rated walls. Phone #: ###-#### Inspection requested via web by Joel Hartman south side of 51 parapet penatrations ok to finsh// north side need corected
|
BLD-Other | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | CANC |
Jim Storey
|
|
|
They are trying to get the pipes insulated on the east side penetrations through the rated wall Bldg 50/51. Could you take a look at them this afternoon. Contact Greg Baisch, ###-#### Phone #: ###-#### >> Inspection requested via web by Joel Hartman Inspection cancelled from web by: Joel Hartman
|
BLD-Conference | 8/17/2017 | 8/17/2017 | 8/17/2017 | P | DONE |
Jim Storey
|
|
|
Meet to walk Stage C competition, East side Chem rooms. Erik Holinka''s phone number above. Phone #: ###-#### walk thru to verify microns protocall for chem rooms
|
BLD-Other | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | DEFR |
Jim Storey
|
|
|
Meet to walk Stage C competition, East side Chem rooms. Erik Holinka''s phone number above. Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Other | 7/11/2017 | 7/12/2017 | 7/13/2017 | P | PART |
Bob Archibald
|
|
|
TCO inspection Phone #: ###-#### Inspection requested via web by Joel Hartman. A "staged construction " review was conducted to addrerss exiting and rated construction for zone B51.1 the inspection was NOT to establish a Temp. CO.. Minor work is still required on fire rated construction ( stair enclosure, exit coridoor and building seperation) and egress systems (doors/hardware, landings stairways and exit signage). The contractor was informed of code provisions to complete rated wall construction, membrane/ through penetrations and rated door requirements. Provisions for maintaining clear paths of egress, door hardware, level landings and exit signage requirements. Exiting doors and means of egress into building 50 need to be addressed as these were originally exterior doors.
|
BLD-Other | 7/11/2017 | 7/12/2017 | 7/12/2017 | A | DEFR |
Jim Storey
|
|
|
TCO inspection Phone #: ###-#### Inspection requested via web by Joel Hartman
|
FIRE-Final Inspection | 7/10/2017 | 7/11/2017 | 7/11/2017 | P | PART |
Jim Page
|
|
|
Power transfer from normal power source to emergency power for egress lighting complete in TCO requested area (Northwest Basement level, level 1 and level 2 mechanical)
|
BLD-Other | 7/7/2017 | 7/10/2017 | 7/11/2017 | P | NR |
Jim Storey
|
|
|
TCO Inspection Phone #: ###-#### Inspection requested via web by Joel Hartman
|
FIRE-Final Inspection | 7/6/2017 | 7/10/2017 | 7/10/2017 | A | PART |
Jim Page
|
|
|
James Phone #: ###-#### has punchlist items from life fire safety conference for TCO requested area, remaining items left to address for TCO reuqested area is the card read secure doors in the basment level and mech 30 level link between existing building and new building, these doors are part of the path of egress, door swing is going against the path of travel, door swing needs to be corrected.
|
BLD-Other | 6/1/2017 | 6/1/2017 | 6/1/2017 | A | NH |
Jim Storey
|
|
|
Inspect blow-on fireproofing. This is for Greg Baisch. Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Other | 5/30/2017 | 5/31/2017 | 6/1/2017 | P | DEFR |
Dave Hannah
|
|
|
Inspect blow-on fireproofing. This is for Greg Baisch. Phone #: ###-#### Inspection requested via web by Joel Hartman
|
BLD-Other | 5/24/2017 | 5/25/2017 | 5/25/2017 | P | PASS |
Jim Storey
|
|
|
Looking at fire penetrations. Phone #: ###-#### Inspection requested via web by Joel Hartman gas line penatrations ok to plate both sides as per listting and egineered listing.
|
BLD-Conference | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Jim Storey
|
|
|
firestopping training for site personal by hilt book under assembly as to firestopping and ul for each tradei.
|
BLD-Conference | 4/13/2017 | 4/17/2017 | 4/17/2017 | A | DONE |
Jim Storey
|
|
|
10:00 AM Phone #: ###-#### Inspection requested via web by Joel Hartman requiring firestopping submitals
|
BLD-Conference | 4/12/2017 | 4/14/2017 | 4/14/2017 | P | DONE |
Jim Storey
|
|
|
appt: with paul walk about 1:30
|
BLD-Framing/Rough-in | 4/11/2017 | 4/11/2017 | 4/11/2017 | A | FAIL |
Jim Storey
|
|
|
wall defeltion stud removal at duct pentrations/ fire stopping listings from all trades for penatrating idems and rattings, type of matrial used/door listings and aplactions 3 hr/ gyp to concrete rated joints.
|