Permit Information
Permit NumberBLD17-00102
StatusIssued
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 8000 S FEDERAL WAY
Project NameMicron TCUP Bldg
Customer NumberC24074
ePlanReviewYes
Description
**Project Management-Ron Hill**(MICRON)(TCUP BLDG) For the construction of a new 4,900 sq. ft. central utilities building to serve R&D Fab Bldg. 51 with work to include general site work, footings, foundation and consruction of the steel building including mechanical, electrical and plumbing per the approved plan and the attached engineering. This building is fully fire sprinklered. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection5/27/20205/27/20205/27/2020 PASS
DetailsJim Storey
BLD-Final1/14/20201/14/20201/14/2020PPASS
DetailsJim Storey
dillion
BLD-Final1/9/20201/10/20201/10/2020PFAIL
DetailsJim Storey
dillon Phone #: ###-#### pw and achd no sig on card.
FIRE-Final Inspection12/19/201912/20/201912/20/2019PPASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete (fire alarm is with B51 fire alarm submittal, B51 fire aalrm permit will remain in issued status until fire alarm inspection for B51 is complete), fire extinguishers are placed with current inspection tags. Final life fire safety inspection for TCUP complete..

tea cup // Dillon Phone #: ###-####
FIRE-Final Inspection10/14/201910/14/201910/14/2019PFAIL
DetailsJim Page
Povide permit for fire alarm install as discussed.

Final for Fire/Life Safety - TCUP Phone #: ###-#### Inspection requested via web by Dillon Barresi
BLD-Conference4/3/20194/3/20194/3/2019APEND
DetailsJim Storey
Expires: 08/01/18
BLD-Aging Inspection2/2/20182/2/20182/2/2018 PASS
DetailsJim Storey
wip
BLD-Conference8/25/20178/25/20178/25/2017APASS
DetailsJim Storey
walk thru prep for final/ landings doors/equment tie down boliers