Information based on query as of Thursday, May 16, 2024.
Permit Information
Permit NumberBLD17-00644
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 6779 W TARGEE ST
Project NameJordan Wilcomb Warehouse
Customer Number 
ePlanReviewYes
Description
(JORDAN WILCOMB WAREHOUSE) **Permit for the construction of a new 9,600 sq. ft. pre-engineered shell storage building and related site improvements. Scope of work includes: construction of slab on grade concrete foundation, pre-engineered shell with insulation, interior non-bearing walls, restroom, electrical, mechanical, plumbing, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. All work shall comply with the approved plans, DRH16-00233 and all applicable codes. This building is NOT Fire Sprinklered. Note: Special Inspections Required, see form 310. Note: complies with ANSI/ASHREA 90.1. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/28/20183/1/20183/1/2018PPASS
DetailsBrandon Shaw
Planning ; zoning just signed off. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen
DOC - Permit Finaled3/1/20183/1/20183/1/2018PPASS
DetailsBrandon Shaw
FIRE-Final Inspection2/19/20182/20/20182/20/2018PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection2/6/20182/7/20182/7/2018PFAIL
DetailsTroy Cobbley
Repair the north end exit signs, repair the bay emergency lights, provide annual inspection for the fire extinguishers, provide small documents.


Phone #: ###-#### Inspection requested via web by Mark Steen
BLD-Ceiling Grid Inspection1/22/20181/23/20181/23/2018APASS
DetailsMike Jordan
12'' x 18'' storage room Phone #: ###-#### Inspection requested via web by Mark Steen
BLD-Framing/Rough-in12/14/201712/15/201712/15/2017APART
DetailsMike Jordan
Just two small rooms with metal studs. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen. Interior steel stud framed walls and hardlid only. Pending mech. and plumbing rough in inspections.
BLD-Foundation7/28/20177/31/20177/31/2017ADEFR
DetailsMike Jordan
MTI to check rebar and test concrete. The pour is scheduled for 10am. thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Special inspector on site.
BLD-Footing7/26/20177/27/20177/27/2017APART
DetailsMike Jordan
MTI to Insp ftgs and concrete. Scheduled to pour at noon. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Work in progress on perimeter footings. Will have special inspection.