BLD-Final | 12/9/2017 | 12/12/2017 | 12/12/2017 | A | PASS |
Dave Hannah
|
|
|
Looks like we have our MECH final! REady to go for final c of o i hope! Key is in the mailbox for inspection. If possible, please call with approximate time for inspection and he will be there too. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
DOC - Permit Finaled | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | NR |
Dave Hannah
|
|
|
Home is ready for final. Please call or text with approximate inspection time and I will gladly meet with you at the site as needed. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Final | 12/4/2017 | 12/6/2017 | 12/6/2017 | P | NR |
Dave Hannah
|
|
|
Inspection for final and C of O. Thanks, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Conference | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | DONE |
Dave Hannah
|
|
|
Would like a site meeting to discuss a couple items for completion. Please call to arrange a time to meet. I will be flexible to your schedule. thank you, steve 208.850.8424. Phone #: ###-#### Inspection requested via web by steve hanson winder stairs not to code
|
BLD-Framing/Rough-in | 8/17/2017 | 8/18/2017 | 8/18/2017 | P | PASS |
Dave Hannah
|
|
|
INspection for cut floor truss at laundry chute in basement. Please call with any questions. steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Energy code compliance | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Framing/Rough-in | 8/9/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Brandon Shaw
|
|
|
Framing inspection done with insulation blaket in place- foam/caulk done prior to low voltage instalation. 1) Draft stop/ fire block Mech chace at basement and first floor
Procced at own risk
|
BLD-Framing/Rough-in | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | NR |
Jim Storey
|
|
|
Framing inspection. Plans are near the fireplace. thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson Need all other trades rough in prior to framing
|
BLD-Framing/Rough-in | 8/2/2017 | 8/7/2017 | 8/7/2017 | P | FAIL |
Brandon Shaw
|
|
|
Need all other trades rough in prior to framing
|
BLD-Framing/Rough-in | 8/2/2017 | 8/4/2017 | 8/2/2017 | P | CANC |
Dave Hannah
|
|
|
Framing inspection. Please call with approximate time you will be at the site and we will try to attend. thank you, Mike. Phone #: ###-#### >> Inspection requested via web by steve hanson Inspection cancelled from web by: steve hanson
|
BLD-Other | 7/21/2017 | 7/24/2017 | 7/24/2017 | A | PASS |
Dave Hannah
|
|
|
Complaint of building materials blocking public sidewalk. sidewalk has been cleared
|
BLD-Wall Bracing | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Foundation | 6/7/2017 | 6/8/2017 | 6/8/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo Location Lira
|
BLD-Footing | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: 9495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Foundation | 5/17/2017 | 5/18/2017 | 5/19/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo Lira
|
BLD-Footing | 5/8/2017 | 5/9/2017 | 5/9/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira
|
BLD-Other | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PASS |
Dave Hannah
|
|
|
Erosion control and grading inspection please. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|