Description
ARBOR CROSSING APARTMENTS. (REPAIR PERMIT) This permit is for the repair of fire damaged units. Per the contractor and owner all structural elements with any char damage are being replaced per the original constructions documents which includes a few beams and several trusses. All unit separation walls and building separation walls are required to be replaced per the original construction documents. A pre-inspection conference with the building inspector is required prior to the start of any reconstruction. This is a scope of work permit only with a certificate of completion to be issued upon completion and approval of this project. This building is not fire sprinklered. All exterior work is required to match the existing construction. See the attached plan review report for window replacement requirements. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/6/20184/6/20184/6/2018PPASS
DetailsTony Young
Phone #: ###-####
DOC - Permit Finaled4/6/20184/6/20184/6/2018PPASS
DetailsTony Young
c of c issued
BLD-Final3/30/20184/2/20184/2/2018PNR
DetailsTony Young
Inspection requested via web by Bryan Toole,, needs handrails per code
BLD-Final3/29/20183/30/20183/30/2018APART
DetailsTony Young
Contact: Bryan ###-#### Inspection requested via web by Bryan Toole,, needs self closers on doors,(doors are per schedule on reviewed plan), handrails on wall side in stairwell
FIRE-Final Inspection3/28/20183/29/20183/29/2018APASS
DetailsJim Page
Fire alarm inspection complete, no fire sprinklers, fire extinguishers are in place with current inspection tags, addressing will be installed before building final. Final life fire safety inspection complete.
FIRE-Final Inspection3/27/20183/28/20183/28/2018ACANC
DetailsJim Page
Spoke with point of contacy, Brian Toole Phone #: ###-####, fire extinguishers are not in place, inspection request will be rescheduled after fire extinguishers are placed. This request is cancelled.
BLD-Conference3/6/20183/8/20183/8/2018PPASS
DetailsTony Young
Project status?,, all prior issues were made ok,, will final w/in the next 2 weeks
BLD-Conference12/21/201712/21/201712/21/2017PPASS
DetailsTony Young
Inspection requested via web by Bryan Toole,, fire caulking,, work in progress,, ok
BLD-Framing/Rough-in12/20/201712/21/201712/21/2017APART
DetailsTony Young
Framing and HVAC Rough inspection needed Inspection requested via web by Bryan Toole,, ok to cover except dryer vent areas
BLD-Framing/Rough-in12/20/201712/21/201712/20/2017ACANC
DetailsTony Young
>> Inspection requested via web by Bryan Toole Inspection cancelled from web by: Bryan Toole
BLD-Framing/Rough-in12/18/201712/19/201712/19/2017ANR
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Bryan Toole
BLD-Framing/Rough-in12/13/201712/13/201712/13/2017APART
DetailsJim Storey
ok to dry wall septration wall/ ceillings of upper units
BLD-Framing/Rough-in12/12/201712/13/201712/13/2017APART
DetailsJim Storey
Also can contact Art ###-#### Phone #: ###-#### Inspection requested via web by Bryan Toole ok to insulate walls/ need duct 2 and 3 rd floors moved to tunnel gyp cons// fire chalk and patch ceilling tunnels/ ele service ceilling// washer boxes and dryer vents in exit to be addressed with bill v.
BLD-Conference11/15/201711/17/201711/17/2017APART
DetailsTony Young
Check status of project?,, trades look like they will start soon
BLD-Conference11/14/201711/15/201711/16/2017PPEND
DetailsTony Young
Check status of project?
BLD-Conference11/9/201711/14/201711/14/2017ADEFR
DetailsTony Young
Check status of project?
BLD-Conference11/6/201711/9/201711/9/2017APEND
DetailsTony Young
Check status of project?,, exterior painters working,, left a card in the door,, no other work at this point
BLD-Conference11/2/201711/6/201711/6/2017APEND
DetailsTony Young
Check status of project?
BLD-Conference11/1/201711/2/201711/2/2017APART
DetailsTony Young
Check status of project?,, trades are working
BLD-Conference10/31/201711/1/201711/1/2017APEND
DetailsTony Young
Check status of project?
BLD-Conference5/16/20175/17/20175/17/2017PPASS
DetailsTony Young
Jared Phone #: ###-####,, general ?s and got to see the project