BLD-Final | 4/6/2018 | 4/6/2018 | 4/6/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
DOC - Permit Finaled | 4/6/2018 | 4/6/2018 | 4/6/2018 | P | PASS |
Tony Young
|
|
|
c of c issued
|
BLD-Final | 3/30/2018 | 4/2/2018 | 4/2/2018 | P | NR |
Tony Young
|
|
|
Inspection requested via web by Bryan Toole,, needs handrails per code
|
BLD-Final | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | PART |
Tony Young
|
|
|
Contact: Bryan ###-#### Inspection requested via web by Bryan Toole,, needs self closers on doors,(doors are per schedule on reviewed plan), handrails on wall side in stairwell
|
FIRE-Final Inspection | 3/28/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
Jim Page
|
|
|
Fire alarm inspection complete, no fire sprinklers, fire extinguishers are in place with current inspection tags, addressing will be installed before building final. Final life fire safety inspection complete.
|
FIRE-Final Inspection | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | CANC |
Jim Page
|
|
|
Spoke with point of contacy, Brian Toole Phone #: ###-####, fire extinguishers are not in place, inspection request will be rescheduled after fire extinguishers are placed. This request is cancelled.
|
BLD-Conference | 3/6/2018 | 3/8/2018 | 3/8/2018 | P | PASS |
Tony Young
|
|
|
Project status?,, all prior issues were made ok,, will final w/in the next 2 weeks
|
BLD-Conference | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Tony Young
|
|
|
Inspection requested via web by Bryan Toole,, fire caulking,, work in progress,, ok
|
BLD-Framing/Rough-in | 12/20/2017 | 12/21/2017 | 12/21/2017 | A | PART |
Tony Young
|
|
|
Framing and HVAC Rough inspection needed Inspection requested via web by Bryan Toole,, ok to cover except dryer vent areas
|
BLD-Framing/Rough-in | 12/20/2017 | 12/21/2017 | 12/20/2017 | A | CANC |
Tony Young
|
|
|
>> Inspection requested via web by Bryan Toole Inspection cancelled from web by: Bryan Toole
|
BLD-Framing/Rough-in | 12/18/2017 | 12/19/2017 | 12/19/2017 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Toole
|
BLD-Framing/Rough-in | 12/13/2017 | 12/13/2017 | 12/13/2017 | A | PART |
Jim Storey
|
|
|
ok to dry wall septration wall/ ceillings of upper units
|
BLD-Framing/Rough-in | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | PART |
Jim Storey
|
|
|
Also can contact Art ###-#### Phone #: ###-#### Inspection requested via web by Bryan Toole ok to insulate walls/ need duct 2 and 3 rd floors moved to tunnel gyp cons// fire chalk and patch ceilling tunnels/ ele service ceilling// washer boxes and dryer vents in exit to be addressed with bill v.
|
BLD-Conference | 11/15/2017 | 11/17/2017 | 11/17/2017 | A | PART |
Tony Young
|
|
|
Check status of project?,, trades look like they will start soon
|
BLD-Conference | 11/14/2017 | 11/15/2017 | 11/16/2017 | P | PEND |
Tony Young
|
|
|
Check status of project?
|
BLD-Conference | 11/9/2017 | 11/14/2017 | 11/14/2017 | A | DEFR |
Tony Young
|
|
|
Check status of project?
|
BLD-Conference | 11/6/2017 | 11/9/2017 | 11/9/2017 | A | PEND |
Tony Young
|
|
|
Check status of project?,, exterior painters working,, left a card in the door,, no other work at this point
|
BLD-Conference | 11/2/2017 | 11/6/2017 | 11/6/2017 | A | PEND |
Tony Young
|
|
|
Check status of project?
|
BLD-Conference | 11/1/2017 | 11/2/2017 | 11/2/2017 | A | PART |
Tony Young
|
|
|
Check status of project?,, trades are working
|
BLD-Conference | 10/31/2017 | 11/1/2017 | 11/1/2017 | A | PEND |
Tony Young
|
|
|
Check status of project?
|
BLD-Conference | 5/16/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Tony Young
|
|
|
Jared Phone #: ###-####,, general ?s and got to see the project
|