BLD-Final | 10/24/2018 | 10/26/2018 | 10/26/2018 | P | DONE |
Tony Young
|
|
|
Call half hour before // Barbra Phone #: ###-####
|
DOC - Permit Finaled | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 10/22/2018 | 10/24/2018 | 10/24/2018 | A | PART |
Tony Young
|
|
|
Call half hour before // Barbra Phone #: ###-####,, ok pending zoning
|
BLD-Final | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PEND |
Tony Young
|
|
|
Call half hour before // Barbra Phone #: ###-####
|
BLD-Final | 10/19/2018 | 10/19/2018 | 10/19/2018 | P | PEND |
Tony Young
|
|
|
Call half hour before // Barbra Phone #: ###-####,, ok pending historical
|
BLD-Framing/Rough-in | 6/27/2018 | 6/28/2018 | 6/28/2018 | P | PEND |
Tony Young
|
|
|
Tom Phone #: ###-####,, needs mech. permit prior to cover
|
BLD-Framing/Rough-in | 6/26/2018 | 6/27/2018 | 6/27/2018 | P | PART |
Tony Young
|
|
|
Tom Phone #: ###-####,, same as last notes
|
BLD-Framing/Rough-in | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | PART |
Tony Young
|
|
|
Tom Phone #: ###-####,, needs a mech permit,, ok to start covering unaffected areas,, need some fire blocking,, insulate the rim,, seal the top plates
|
BLD-Foundation | 5/16/2018 | 5/17/2018 | 5/17/2018 | A | PASS |
Tony Young
|
|
|
wall// Layllon Phone #: ###-####,, last portion ok,, work in progress
|
BLD-Footing | 4/23/2018 | 4/23/2018 | 4/23/2018 | P | PASS |
Tony Young
|
|
|
Waylon-(did foundation work) Phone #: ###-####,, west wall,, north 1/3
|
BLD-Foundation | 4/4/2018 | 4/5/2018 | 4/5/2018 | A | PART |
Tony Young
|
|
|
Waylon Phone #: ###-####,, south part,, work in progress,, ok
|
BLD-Footing | 3/27/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Dave Hannah
|
|
|
Waylon Phone #: ###-####
|
BLD-Foundation | 3/19/2018 | 3/20/2018 | 3/20/2018 | A | PART |
Tony Young
|
|
|
Waylon Phone #: ###-####,, north/west north wall ok after adding on to a couple of splice areas,, also mid section of west wall ok to shotcrete
|
BLD-Foundation | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | NR |
Tony Young
|
|
|
Waylon Phone #: ###-####
|
BLD-Foundation | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | NR |
Dave Hannah
|
|
|
Waylon Phone #: ###-####
|
BLD-Footing | 3/13/2018 | 3/14/2018 | 3/15/2018 | A | PART |
Dave Hannah
|
|
|
Wayln Phone #: ###-#### secon d phase by opennig
|
BLD-Foundation | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PART |
Dave Hannah
|
|
|
rebar - Jeff Phone #: ###-#### first wall section rebar ok
|
BLD-Footing | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PART |
Dave Hannah
|
|
|
Jeff-pour time 1:00 Phone #: ###-#### first section of ftg part of back wall and 2/3sd of north wall ok to pour
|
BLD-Footing | 2/8/2018 | 2/9/2018 | 2/9/2018 | P | PART |
Dave Hannah
|
|
|
Jeff-pour time 3:00 Phone #: ###-#### two column ftgs ok to pour
|