BLD-Final | 6/20/2018 | 6/21/2018 | 6/21/2018 | P | PASS |
Jim Sly
|
|
|
Steve Phone #: ###-####
|
FIRE-Final Inspection | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per the contractor the new inner gate, at the main gate, is also connected to the opticon system.
Steve Phone #: ###-####
|
BLD-Final | 6/5/2018 | 6/7/2018 | 6/7/2018 | A | PART |
Jim Sly
|
|
|
Steve Phone #: ###-#### Temp OK.
|
FIRE-Final Inspection | 6/5/2018 | 6/6/2018 | 6/6/2018 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until the permanant building designations have been mounted (A, B, C...ect.). The west most fire hydrant is being rotated per the fie captain.
Steve Phone #: ###-####
|
FIRE-Final Inspection | 6/1/2018 | 6/4/2018 | 6/4/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the exit discharge, on the east Office building door repaired and provided with a secondary power source, Repair the exit sign/emergency light/exit discharge light in the west corridor of BLDG K, Provide testing of the Opticon system at the main gate. get fire dept approval for the west side fire hydrant (barrel points to bollard)
Steve Phone #: ###-####
|
BLD-Foundation | 10/2/2017 | 10/2/2017 | 10/2/2017 | P | PASS |
Jim Sly
|
|
|
requ 2:30 // frost wall insp // Steve Phone #: ###-#### OK pending STRATA special inspection, tests and approvals.
|