BLD-Final | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Tony Young
|
|
|
Please call ahead for access - Jeffrey Phone #: ###-####// c of o issued,, blower door is 3.9
|
DOC - Permit Finaled | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Other | 1/29/2019 | 1/29/2019 | 1/29/2019 | P | DONE |
Bob Archibald
|
|
|
Received recorded easment
|
BLD-Final | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | NR |
Tony Young
|
|
|
Doug Phone #: ###-####,, needs trades passed,, sewer line issues,, c/n posted to resolve sewer line easment or reroute adjacent property owners sewer line with approvals from under this home. will also need a blower door test result
|
BLD-Energy code compliance | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Dave Hannah
|
|
|
Rob Phone #: ###-####
|
BLD-Framing/Rough-in | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PASS |
Tony Young
|
|
|
Rob Phone #: ###-####,, front house meets plans now,, ok to insulate
|
BLD-Conference | 6/4/2018 | 6/4/2018 | 6/4/2018 | P | FAIL |
Tony Young
|
|
|
Rob Phone #: ###-####,, met with contractor,, he had reviewed plans,, needs to get approval from olan review and get ok as built.. remove or get approval as built or remove 220 in kitchen upstairs
|
BLD-Framing/Rough-in | 6/1/2018 | 6/4/2018 | 6/4/2018 | A | FAIL |
Tony Young
|
|
|
Rob Phone #: ###-####,, no plans,, needs to remove 220 v circuit all the way out unless approved by the plan review
|
BLD-Conference | 5/16/2018 | 5/17/2018 | 5/17/2018 | A | FAIL |
Tony Young
|
|
|
Rob Phone #: ###-####,, walk through only,, need plans,, elevation cert,, take out added ADU components
|
BLD-Framing/Rough-in | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | FAIL |
Tony Young
|
|
|
- Rob Phone #: ###-####,, need city set of plans
|
BLD-Conference | 5/4/2018 | 5/4/2018 | 5/7/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need to provide city approved set of plans
|
BLD-Framing/Rough-in | 4/27/2018 | 4/30/2018 | 4/30/2018 | A | FAIL |
Tony Young
|
|
|
Rob Phone #: ###-####,, need the reviewed plans on site
|
BLD-Framing/Rough-in | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | FAIL |
Tony Young
|
|
|
Rob Phone #: ###-####,, need plans and truss engineering,, need to verify how many dwelling units are under one roof
|
BLD-Framing/Rough-in | 4/17/2018 | 4/18/2018 | 4/18/2018 | A | FAIL |
Tony Young
|
|
|
Rob Phone #: ###-####,, need plans
|
BLD-Wall Bracing | 3/19/2018 | 3/20/2018 | 3/20/2018 | P | PEND |
Brandon Shaw
|
|
|
Work in progress Walked through with framer- Hold down, edge, and field nailing to be fixed by framing inspection
|
BLD-Wall Bracing | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | NR |
Tony Young
|
|
|
Rob Phone #: ###-####,, see paint marks
|
BLD-Foundation | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | FAIL |
Jim Storey
|
|
|
James Phone #: ###-#### placed with out insp.
|
BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | PASS |
Tony Young
|
|
|
James Phone #: ###-####
|