BLD-Final | 5/2/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Mike Jordan
|
|
|
Will Phone #: ###-####. OK for perm occ.
|
BLD-Final | 4/30/2018 | 5/1/2018 | 5/1/2018 | P | PART |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Ok for temp occ. Needs to provide 20 min rated doors at sleeping rooms.
|
FIRE-Final Inspection | 4/30/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Bill Phone #: ###-####
|
FIRE-Final Inspection | 4/25/2018 | 4/26/2018 | 4/26/2018 | P | FAIL |
Troy Cobbley
|
|
|
No small documents on site, no address, generator had not been commissioned yet. Door hardware appears ok.
bill Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Wall Bracing | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | CANC |
Mike Jordan
|
|
|
Concrete at 10:45 // Bill Phone #: ###-####
|
BLD-Footing | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Footing for generator enclosure.
|
BLD-Energy code compliance | 2/7/2018 | 2/7/2018 | 2/7/2018 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Framing/Rough-in | 1/30/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####. roof ok. Interior wood framed walls, shearwalls and roof joist ok. ok to insulate.
|
BLD-Wall Bracing | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Exterior and Interior shear walls.
|
BLD-Other | 1/2/2018 | 1/2/2018 | 1/2/2018 | P | PART |
Mike Jordan
|
|
|
Masonary/structural steel - Bill Phone #: ###-####. 4ft. to 8ft. elevation on interior non bearing CMU wall.
|
BLD-Other | 12/19/2017 | 12/20/2017 | 12/20/2017 | A | DEFR |
Mike Jordan
|
|
|
late AM ealy PM // structural steel and masonry, MTI is inspecting too // Bil Tonkin Phone #: ###-####. Special inspector on site.
|
BLD-Other | 12/18/2017 | 12/19/2017 | 12/19/2017 | A | CANC |
Mike Jordan
|
|
|
late AM ealy PM // structural steel and masonry, MTI is inspecting too // Bil Tonkin Phone #: ###-####. Cancelled by contractor via phone call.
|
BLD-Other | 12/15/2017 | 12/18/2017 | 12/18/2017 | A | DEFR |
Mike Jordan
|
|
|
pour at 10 // Bill Phone #: ###-####. Special inspector on site.
|
BLD-Other | 12/13/2017 | 12/14/2017 | 12/14/2017 | A | PART |
Mike Jordan
|
|
|
Steal and CMU block (MTI) ..... Late morning please // Bill Phone #: ###-####. Work in progress on perimeter walls from 4ft. to 8ft. elevation. Speciial inspector will be on site at time of grout placement.
|
BLD-Concrete | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | CANC |
Brandon Shaw
|
|
|
rebar - late morning - Bill Phone #: ###-####
|
BLD-Foundation | 11/7/2017 | 11/8/2017 | 11/8/2017 | A | PART |
Mike Jordan
|
|
|
Rebar stem wall... pour at 2 // Bill Phone #: ###-####. Work in progress on interior footings and perimeter sremwalls. ok to place concrete after special inspection has pssed.
|
BLD-Foundation | 11/1/2017 | 11/3/2017 | 11/3/2017 | A | CANC |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 11/3/2017 | 11/3/2017 | 11/3/2017 | A | PART |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Work in progress on perimeter footings. Will have special inspections.
|