BLD-Final | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Brandon Shaw
|
|
|
Eric Phone #: ###-####
|
DOC - Permit Finaled | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Conference | 9/28/2018 | 9/28/2018 | 9/28/2018 | A | DEFR |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 | | DEFR |
Brandon Shaw
|
|
|
|
BLD-Other | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
Brandon Shaw
|
|
|
Eric---soffit inspection Phone #: ###-####
|
BLD-Energy code compliance | 5/16/2018 | 5/17/2018 | 5/17/2018 | A | PASS |
Brandon Shaw
|
|
|
Eric Phone #: ###-####
|
BLD-Framing/Rough-in | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 5/8/2018 | 5/9/2018 | 5/9/2018 | A | CANC |
Brandon Shaw
|
|
|
Eric Phone #: ###-####
|
BLD-Foundation | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Brandon Shaw
|
|
|
Ready as of yesterday. Would like to pour mid morning if that works Please call Phone #: ###-#### Inspection requested via web by Ben Sears
|
BLD-Footing | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Request early inspection Phone #: ###-#### Inspection requested via web by Ben Sears
|
BLD-Foundation | 12/14/2017 | 12/14/2017 | 12/14/2017 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
Frost protection required
|
BLD-Footing | 11/15/2017 | 11/15/2017 | 11/15/2017 | A | PART |
Brandon Shaw
|
|
|
Phase I, footings
Exterior Column footings at a later time
|
BLD-Footing | 11/15/2017 | 11/15/2017 | 11/15/2017 | A | CANC |
Brandon Shaw
|
|
|
request inspection around 11 Phone #: ###-#### Inspection requested via web by Ben Sears
|