Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberBLD17-02932
StatusFinaled
Name SLOANCO LLC
Site Address 6828 W MELROSE ST
Project NameSloanCo - Office, Fab, Storage
Customer Number 
ePlanReviewYes
Description
(SLOANCO – OFFICE, FABRICATION, WAREHOUSE – NEW BUILDING AND TENANT IMPROVEMENT) (DRH17-00279) The fire sprinkler system will be used for building area increase, story increase, and for fire area. To construct a new 17,645 square foot building (14,659 square feet 1st story and 2,986 square feet 2nd story) to be used for office, fabrication, and storage. A grading permit (GRD17-00044) was issued earlier. A foundation permit (BLD17-03338) was also issued earlier and was for excavation, fill compaction, footings, and foundations for the building only. To erect a pre-engineered metal building with a wood framed 2 story office component below the roof of the metal building. The metal building work is to include steel columns, steel beams, steel purlins, metal siding, metal roof deck, and steel bracing. The wood framed office work is to include wood exterior bearing and nonbearing walls, stone veneer, 3-part stucco system, metal siding, wood interior bearing and nonbearing walls, wood floor trusses, wood floor sheathing, wood shear walls, an interior stairway, an exterior steel stairway, exterior doors, exterior windows, interior doors, interior windows, millwork, and finishes. Special Inspection is required for soils, concrete, welding, and bolting. Welding, painting, spraying, and coating operations done within this building as part of its use are required to be in compliance with the Fire Code. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. A separate permit is required for storage racks exceeding 8 feet in height. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/29/20188/30/20188/30/2018APASS
DetailsMike Jordan
Greg Phone #: ###-####. All issues resolved. ok for perm occ.
BLD-Aging Inspection7/11/20187/11/20187/11/2018 PEND
DetailsMike Jordan
pending zoning and fees due.
BLD-Final4/19/20184/19/20184/19/2018PPART
DetailsMike Jordan
Ok for temp occ. Still needs to install a permanant cane guard.
BLD-Final4/18/20184/19/20184/19/2018AFAIL
DetailsMike Jordan
Greg Phone #: ###-####. Provide cane guard on exterior stairs. Noted open risers on exterior stairs exceed 4 inches. Also needs final letter from special insection.
FIRE-Final Inspection4/17/20184/18/20184/18/2018APASS
DetailsTroy Cobbley
life safety passed

Greg Phone #: ###-####
FIRE-Final Inspection4/17/20184/17/20184/17/2018PCANC
DetailsTroy Cobbley
Greg Phone #: ###-####
BLD-Final4/16/20184/16/20184/16/2018PNR
DetailsMike Jordan
Greg -structural final occupancy Phone #: ###-####
FIRE-Final Inspection4/16/20184/16/20184/16/2018PFAIL
DetailsJim Page
Fire extinguishers are mounted to high, extinguishers need to be lowered to 48inches or below. Provide signage for fire sprinkler riser room/FACP. Repair exit discharge emergency lighting, exterior emergency lights did not work on secondary power supply.
BLD-Ceiling Grid Inspection3/13/20183/14/20183/14/2018APART
DetailsMike Jordan
Ed Phone #: ###-####. Grid ok 1st and 2nd floors. Pending electrical and mech. rough in inspections.
FIRE-Conference3/7/20183/7/20183/7/2018PDONE
DetailsTroy Cobbley
I stopped and discussed possible gate requirements with the job superintendant. Per scott the reduced gate width is not a factor and the electric gates (submitted as manual) will not require Opticon but a means to access them shall be required to be provided in the Knox key box
BLD-Energy code compliance3/6/20183/6/20183/6/2018PPASS
DetailsBrandon Shaw
Ed Phone #: ###-####
BLD-Energy code compliance2/9/20182/9/20182/9/2018PPASS
DetailsMike Jordan
Ed Phone #: ###-####
BLD-Energy code compliance2/6/20182/7/20182/7/2018PPASS
DetailsJim Storey
Ed Phone #: ###-#### 2nd floor ok/ first floor ok to insulate pending fir spk hard ceillings ok
BLD-Framing/Rough-in2/2/20182/5/20182/5/2018APASS
DetailsMike Jordan
Ed Phone #: ###-####. Interior and exterior wood framed walls 2nd. floor only ok. No ceiling or hardlids at this time.
BLD-Framing/Rough-in2/1/20182/2/20182/2/2018ACANC
DetailsMike Jordan
ED SLOAN Phone #: ###-####. Needs electrical rough in inspection and airseal pack .
BLD-Framing/Rough-in1/10/20181/11/20181/11/2018APASS
DetailsMike Jordan
Ed Phone #: ###-####. Shear walls ok.