BLD-Final | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
DOC - Permit Finaled | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 2/15/2018 | 2/15/2018 | 2/15/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover. Wrong permit called in.
|
BLD-Energy code compliance | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Framing/Rough-in | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Framing/Rough-in | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover. Install the lateral brace on the G01 truss as shown on the truss engineering. Ok to insulate. Correction notice posted.
|
BLD-Framing/Rough-in | 2/2/2018 | 2/6/2018 | 2/6/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kelly Stover Inspection cancelled from web by: Kelly Stover
|
BLD-Wall Bracing | 1/26/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Wall Bracing | 1/24/2018 | 1/26/2018 | 1/26/2018 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover. rescheduled for pm. no approved plans on site.
|
BLD-Wall Bracing | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Foundation | 12/14/2017 | 12/15/2017 | 12/15/2017 | P | PART |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 12/12/2017 | 12/13/2017 | 12/13/2017 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|