BLD-Final | 7/8/2019 | 7/8/2019 | 7/11/2019 | P | PASS |
Dave Hannah
|
|
|
Mixed Aviary BLD final for Occupancy Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
FIRE-Final Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
Mixed Aviary FIre life safety Final, Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Wall cover | 3/13/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Dave Hannah
|
|
|
Approval to cover ceiling in D6 prior to spray foam and Drywall. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Framing/Rough-in | 2/7/2019 | 2/8/2019 | 2/8/2019 | P | PASS |
Dave Hannah
|
|
|
Rody Phone #: ###-####
|
BLD-Energy code compliance | 10/26/2018 | 10/29/2018 | 10/30/2018 | P | CANC |
Dave Hannah
|
|
|
Inspect spray foam insulation prior to hanging drywall Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Wall cover | 10/26/2018 | 10/29/2018 | 10/30/2018 | P | PASS |
Dave Hannah
|
|
|
Inspect to cover ceiling and soffits at D5 Electrical inspections schedule for A.M. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Foundation | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PEND |
Dave Hannah
|
|
|
Building D6 Stem wall rebar. Mti will be on site as well Phone #: ###-#### Inspection requested via web by Brandon Reynolds ok after spec inspection oks
|
BLD-Footing | 10/11/2018 | 10/12/2018 | 10/12/2018 | A | PASS |
Jim Sly
|
|
|
Need rebar inspection for footing. Please call ahead in the morning. Thanks! Phone #: ###-#### Inspection requested via web by Justin Palm OK ....pending MTI special inspection, tests and approvals.
|