BLD-Final | 9/12/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Jim Storey
|
|
|
call me when on site Phone #: ###-#### Inspection requested via web by J.C. Murray final ok pending others
|
FIRE-Final Inspection | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, heat trace inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete, signatures provided on sign off card for associated trades.
call me when on site Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Ceiling Grid Inspection | 6/25/2019 | 6/26/2019 | 6/26/2019 | P | PASS |
Jim Storey
|
|
|
Building j. East 12 units. Drop ceiling fire caulking ceiling for cover. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Ceiling Grid Inspection | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Jim Storey
|
|
|
all drop ceilings ok to cover.
|
BLD-Ceiling Grid Inspection | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | PART |
Jim Storey
|
|
|
Bld J ; north 12 units. fire caulking drop ceilings for cover. Phone #: ###-#### Inspection requested via web by J.C. Murray top north bathrm missing spk/ w/d fire chalk drop.
|
BLD-Framing/Rough-in | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | PASS |
Jim Storey
|
|
|
fire caulking completed for re-inspection Bld J south 12 units. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Ceiling Grid Inspection | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PART |
Jim Storey
|
|
|
Bld J south 12 units. drop ceilings for cover, fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray ok to cover need to verrify rated accesses
|
BLD-Wall cover | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | PART |
Jim Storey
|
|
|
Bld J - all building, air seal and fire caulking for cover. Phone #: ###-#### Inspection requested via web by J.C. Murray toliet flange/ fire blk line sets/tub fur out/ king stud at beams.
|
BLD-Framing/Rough-in | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | PASS |
Jim Storey
|
|
|
Builiding J - exterior nailing, shear straps. hold downs and titan bolts. truss engineering Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Wall Bracing | 11/26/2018 | 11/27/2018 | 11/27/2018 | P | PASS |
Jim Storey
|
|
|
interior shear walls first floor// JC Phone #: ###-####
|
BLD-Energy code compliance | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | PASS |
Jim Storey
|
|
|
exterior foundation insulation Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Foundation | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | PASS |
Jim Storey
|
|
|
wall // manuel Phone #: ###-####
|
BLD-Footing | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PASS |
Jim Sly
|
|
|
Manuel Phone #: ###-#### OK pending MTI special inspections, tests and approvals.
|