BLD-Final | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Tony Young
|
|
|
Ben Phone #: ###-####
|
DOC - Permit Finaled | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | NR |
Tony Young
|
|
|
Ben Phone #: ###-####,, need trades,, hillside
|
BLD-Energy code compliance | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Tony Young
|
|
|
Ben Phone #: ###-####
|
BLD-Other | 4/4/2018 | 4/5/2018 | 4/5/2018 | A | PART |
Tony Young
|
|
|
soffit-Toby-leave tag if passed Phone #: ###-####,, sheet rock soffit areas ok,, other section will be fire rated tongue and groove,, still to verify,, needs rated vents in soffits by the final
|
BLD-Framing/Rough-in | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Tony Young
|
|
|
Van Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 3/28/2018 | 3/28/2018 | 3/28/2018 | A | FAIL |
Mike Jordan
|
|
|
Complete lateral bracing on A03 trusses. Complete all corrections as identified per Tony Young. Ok to insualte. Correction notice posted.
|
BLD-Framing/Rough-in | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | CANC |
Mike Jordan
|
|
|
Ben Phone #: ###-####. rescheduled. wrong entry.
|
BLD-Framing/Rough-in | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | NR |
Tony Young
|
|
|
Ben Phone #: ###-####,, needs mech pass,, dont insulate,, partial walk through
|
BLD-Wall Bracing | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PART |
Tony Young
|
|
|
BEN Phone #: ###-####,, exterior ok to cover,, may need interior later
|
BLD-Wall Bracing | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | NR |
Tony Young
|
|
|
BEN Phone #: ###-####,, re do per plan
|
BLD-Foundation | 2/11/2018 | 2/12/2018 | 2/13/2018 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo,, work in progress,, ok
|
BLD-Footing | 2/8/2018 | 2/9/2018 | 2/9/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|