Permit Information
Permit NumberBLD18-00916
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 400 W FORT ST
Project NameBraves Field Team Room
Customer Number 
ePlanReviewYes
Description
(BRAVES FIELD TEAM ROOM) ""GREEN TAG BOISE SCHOOLS PROJECT"" Permit for the constructio of a new 4,000 Square Foot Team Room for the Braves Field Athletic Complex with work to include general site work and construction of the new building per the approved plans and the attached engineering. This building consists of mens and womens team rooms with restroom facillities, athletic and general equipment storage rooms, public restrooms, concessions and a ticket sales area. This building is not fire sprinklered. Special inspections are required per the attached form 310. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/26/201810/29/201810/29/2018APASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Final9/26/20189/26/20189/26/2018PPART
DetailsDave Hannah
Jan Phone #: ###-#### ok for tco ok for perm oc after landscaping is finised
FIRE-Final Inspection9/24/20189/25/20189/25/2018APASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguisher is placed with current inspection tag. Final life fire safety inspection for area of work complete.

Jane Phone #: ###-####
BLD-Wall Bracing7/27/20187/30/20187/30/2018APASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Energy code compliance6/18/20186/18/20186/18/2018PPASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Foundation6/18/20186/18/20186/18/2018PPASS
DetailsDave Hannah
Jan Phone #: ###-####
BLD-Foundation5/15/20185/16/20185/16/2018APASS
DetailsDave Hannah
Jan- foundation rebar-stem wall Phone #: ###-####
BLD-Footing5/10/20185/11/20185/11/2018APASS
DetailsDave Hannah
Jane Phone #: ###-####