BLD-Final | 12/14/2018 | 12/14/2018 | 12/14/2018 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Larry Kincaid
|
DOC - Permit Finaled | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | DONE |
Jim Sly
|
|
|
Larry Phone #: ###-#### Winders appear.......OK.
|
BLD-Framing/Rough-in | 10/31/2018 | 11/1/2018 | 11/1/2018 | A | DEFR |
Dave Hannah
|
|
|
Larry Phone #: ###-#### sent back to tony
|
BLD-Energy code compliance | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Larry Kincaid. OK to sheet rock. Will need to check winder repair on final.
|
BLD-Framing/Rough-in | 10/12/2018 | 10/12/2018 | 10/12/2018 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Larry Kincaid Everything OK........need to fix winder stirs before final.
|
BLD-Wall Bracing | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Jim Storey
|
|
|
Larry Phone #: ###-####
|
BLD-Other | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PART |
Tony Young
|
|
|
late pm please // slab rebar// pourt at 10 am tomorrow // Larry Phone #: ###-####,, work in progress
|
BLD-Foundation | 8/24/2018 | 8/27/2018 | 8/27/2018 | P | CANC |
Tony Young
|
|
|
rebar // Larry Phone #: ###-####
|
BLD-Foundation | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PART |
Tony Young
|
|
|
John Phone #: ###-####-please go as late as possible ,, work in progress.. rebar in place.. ok
|
BLD-Footing | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | PART |
Tony Young
|
|
|
John Phone #: ###-####-please go as late as possible today,, footing,, work in progress,, property pin in alley on the north east side
|