BLD-Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | DONE |
Tony Young
|
|
|
Justin Phone #: ###-####// c of o issued
|
DOC - Permit Finaled | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | DEFR |
Tony Young
|
|
|
Justin Phone #: ###-####
|
BLD-Final | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | FAIL |
Tony Young
|
|
|
Justin Phone #: ###-####// needs blower door test results, hand rail per code.. fire caulking
|
BLD-Aging Inspection | 9/5/2019 | 9/5/2019 | 9/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 9/4/2019 | 9/4/2019 | 9/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Wall Bracing | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Sly
|
|
|
shear // Justin Phone #: ###-####
|
BLD-Energy code compliance | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Sly
|
|
|
Justin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | FAIL |
Brandon Shaw
|
|
|
See previous entry, Wall Brace...
|
BLD-Wall Bracing | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | FAIL |
Brandon Shaw
|
|
|
Provide revised Engineering for wall bracing- windows and walls added/deleted, not as per plans... Hold downs to be as per plans... Interior WSP to be as per plans... Provide revised plans for as built- Master bath, Fireplace, upstairs bedrooms and baths not as per plans...
|
BLD-Wall Bracing | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | FAIL |
Tony Young
|
|
|
Justin Phone #: ###-####,, needs nailed off per plan
|
BLD-Foundation | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PART |
Tony Young
|
|
|
Gibert Phone #: ###-####
|
BLD-Footing | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PART |
Tony Young
|
|
|
Giber Phone #: ###-####,, work in progress,, new engineering coming,, verified through engineer
|
BLD-Foundation | 10/15/2018 | 10/16/2018 | 10/16/2018 | A | PART |
Tony Young
|
|
|
wall // Sergio Phone #: ###-####,, work in progress,, ok
|