BLD-Final | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PART |
Tony Young
|
|
|
for Temp CO Phone #: ###-#### Inspection requested via web by Josh Strasser,, temp. occupancy ok
|
FIRE-Final Inspection | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags, addressing will be installed when received. Final life fire safety inspection complete.
Josh Phone #: ###-####
|
BLD-Wall cover | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PASS |
Jim Sly
|
|
|
Anchor bolts (2) installed Beam to wall has strap ontop of wall and beam Shear locations (2) nailed Phone #: ###-#### Inspection requested via web by Josh Strasser all Framing.....OK.
|
BLD-Framing/Rough-in | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok to insulate pending trades
|
BLD-Wall Bracing | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Josh Strasser,, exterior ok
|
BLD-Concrete | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Tony Young
|
|
|
Concrete pour is at 11:00 AM Phone #: ###-#### Inspection requested via web by Josh Strasser,, slab work,, SI report
|
BLD-Foundation | 2/5/2019 | 2/8/2019 | 2/8/2019 | A | PART |
Tony Young
|
|
|
Concrete scheduled for 12:30 PM Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok pending special inspection report
|
BLD-Footing | 2/5/2019 | 2/8/2019 | 2/8/2019 | A | PEND |
Tony Young
|
|
|
This was poured and inspected by All West Inspections Phone #: ###-#### Inspection requested via web by Josh Strasser,, pending special inspection report
|