BLD-Final | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.45
|
BLD-Final | 4/9/2019 | 4/10/2019 | 4/10/2019 | P | NR |
Brandon Shaw
|
|
|
Need Mech final...
|
BLD-Blower Door Test Results | 4/9/2019 | 4/10/2019 | 4/10/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.45
|
BLD-Energy code compliance | 2/14/2019 | 2/15/2019 | 2/15/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | FAIL |
Brandon Shaw
|
|
|
Shear corrections not complete...
|
BLD-Wall Bracing | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | FAIL |
Brandon Shaw
|
|
|
All hold downs and anchor bolts to be as per plans and installed per Manufactures installations instructions...
|
BLD-Framing/Rough-in | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | FAIL |
Brandon Shaw
|
|
|
Hold downs to installed per Manuf. Install. instructions... Missing beams and headers- see plans and red paint... Shear wall at back garage wall/rim joist to be as detail A1.2... OK to insulate...
|
BLD-Framing/Rough-in | 1/21/2019 | 1/22/2019 | 1/22/2019 | P | CANC |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Foundation | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | CANC |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 11/5/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|