***PLAN MOD- Modify landscape walls- 12-2-19*** CAT II HILLSIDE, WUI FOOTHILLS, ZONE "A" REQUIREMENTS, CLASS "A" ROOF REQUIRED. |> FIRE SRINKLERS REQUIRED <|
Permit for the construction of a new 3861 sq. ft., two story (first story 2273 sq. ft., second story 1588 sq. ft.) single family dwelling with 5 bedrooms, 3.5 bathrooms, approximately 905 sq. ft. of covered patio/porch and a 971 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. Prescriptive Energy Code is proposed. ***BJM*** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions. Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168. The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final. An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection. All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call 208-608-7168 for an inspection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/4/201912/4/201912/4/2019PPASS
DetailsTony Young
To verify permanent occupany approval. Public Works approved perm.
BLD-Final11/7/201911/7/201911/7/2019PPASS
DetailsTony Young
John Phone #: ###-####,, temp occupancy ok
BLD-Final10/30/201910/30/201910/30/2019PNR
DetailsTony Young
John Phone #: ###-####,, needs hillside approval,, driveway,, hand rails
BLD-Conference9/24/20199/24/20199/24/2019PPART
DetailsTony Young
John Phone #: ###-####,, walk through on final.. hand rails,, trades,, hill side, fire caulking, etc
BLD-Aging Inspection9/6/20199/6/20199/13/2019 PEND
DetailsTony Young
BLD-Aging Inspection9/5/20199/5/20199/6/2019 PASS
DetailsTony Young
BLD-Energy code compliance4/24/20194/24/20194/24/2019PPASS
DetailsTony Young
Phil Phone #: ###-####
BLD-Framing/Rough-in4/15/20194/16/20194/16/2019APART
DetailsTony Young
Phil Phone #: ###-####,, ok to insulate,, needs 1 more sprinkler inspection prior to cover
BLD-Ceiling Grid Inspection4/2/20194/2/20194/2/2019PPART
DetailsTony Young
soffit inspection // Phil Phone #: ###-####,, ok to start covering
BLD-Wall Bracing3/1/20193/1/20193/1/2019PPART
DetailsTony Young
shear// john Phone #: ###-####,, exterior ok
BLD-Footing12/18/201812/18/201812/18/2018PPASS
DetailsBrandon Shaw
Bill-pour time 2:30 Phone #: ###-####1
BLD-Footing12/13/201812/14/201812/14/2018APASS
DetailsTony Young
2 pm pour time- Bill Phone #: ###-####