Permit Information
Permit NumberBLD18-03794
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 2930 S GREBE PL
Project NameShoshone Harris North #1 L67B1
Customer Number 
ePlanReviewYes
Description
|> FULL NFPA 13D SPRINKLER SYSTEM REQUIRED <|
***Prescriptive component energy approach***WUI Zone A requirements*** Permit for the construction of a new 4,240 sq. ft., two story (first story 2,644 sq. ft., second story 1,596 sq. ft.) single family dwelling with 6 bedrooms, 3 and half baths bathrooms, approximately 656 sq. ft. of covered patio/porch and an 816 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. MDH

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/23/20195/24/20195/24/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled5/24/20195/24/20195/24/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results5/24/20195/24/20195/24/2019ADONE
DetailsBrandon Shaw
ACH50- 3.14
BLD-Final5/23/20195/23/20195/23/2019PNR
DetailsBrandon Shaw
Need PLM final...
BLD-Final5/22/20195/23/20195/23/2019ACANC
DetailsBrandon Shaw
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
BLD-Energy code compliance2/12/20192/13/20192/13/2019APASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in2/5/20192/6/20192/6/2019APART
DetailsBrandon Shaw
Provide strap at break in double top plate, single garage, right side bearing wall...
Per plans- DSC connectors to be installed per Engineering...
Need Fire sprinkler tenting approval for attic area sprinklers, before covering...
BLD-Other1/29/20191/29/20191/29/2019PPASS
DetailsBrandon Shaw
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Wall Bracing1/10/20191/11/20191/11/2019APASS
DetailsBrandon Shaw
Work in progress.
BLD-Foundation11/29/201811/30/201811/30/2018APASS
DetailsBrandon Shaw
Work in progress
BLD-Foundation11/28/201811/29/201811/29/2018PNR
DetailsBrandon Shaw
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
BLD-Footing11/27/201811/28/201811/28/2018APASS
DetailsBrandon Shaw
Work in progress...