BLD-Final | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | PASS |
Mike Jordan
|
|
|
Kai Phone #: ###-####
|
BLD-Blower Door Test Results | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | DONE |
Mike Jordan
|
|
|
3.17
|
DOC - Permit Finaled | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PASS |
Mike Jordan
|
|
|
Kai Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2019 | 3/7/2019 | 3/7/2019 | A | FAIL |
Mike Jordan
|
|
|
Kai Phone #: ###-####. Complete lateral bracing on A4 truss. Install the (2) 2x10 headers at furnace in garage to p.u. continous bearing on E2 truss. Install the (2) 2x6 headers over office door to pick up point load on J3 truss. Ok to insulate. Correction notice posted.
|
BLD-Final | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | CANC |
Mike Jordan
|
|
|
Kai Phone #: ###-####
|
BLD-Wall Bracing | 2/13/2019 | 2/13/2019 | 2/13/2019 | A | PASS |
Mike Jordan
|
|
|
Kai Phone #: ###-####
|
BLD-Framing/Rough-in | 2/8/2019 | 2/11/2019 | 2/11/2019 | A | CANC |
Mike Jordan
|
|
|
Kai Phone #: ###-####
|
BLD-Foundation | 1/28/2019 | 1/29/2019 | 1/29/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru. New plans submitted, passed and brought to job site. All corrections made.
|
BLD-Foundation | 1/25/2019 | 1/28/2019 | 1/28/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 1/15/2019 | 1/16/2019 | 1/16/2019 | P | PART |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|