Information based on query as of Sunday, May 12, 2024.
Permit Information
Permit NumberBLD19-00262
StatusIssued
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 487 N MORNINGSIDE WAY
Project NameMorningside Residence
Customer Number 
ePlanReviewYes
Description
CAT II hillside permit **WUI FOOTHILLS ZONE A REQUIREMENTS** **HILLSIDE** **PASSES USING UA TRADE OFF** **310 SPECIAL INSPECTIONS** **Permit includes engineered pool** SPRINKLERS ARE REQUIRED. SEE NOTE ON SITE PLAN G-001. LGM Permit for the construction of a new 4145 sq. ft., two story (first story 2921 sq. ft., basement story 1224 sq. ft.) single family dwelling with 4 bedrooms, 4.5 bathrooms, approximately 1564 sq. ft. of covered patio/porch and a 3124 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. JJN SPRINKLERS ARE REQUIRED. SEE NOTE ON SITE PLAN G-001. LGM
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall Bracing8/12/20208/13/20208/13/2020APART
DetailsDave Hannah
Screened- James Phone #: ###-#### ok to cover ext but shear panel on 7 line needs to be reengineered hold downs in wrong spots and window added.
BLD-Aging Inspection6/4/20206/4/20206/4/2020 DEFR
DetailsBrandon Shaw
Extend Permit 90/180 days6/4/20206/4/20206/4/2020PDONE
DetailsBrandon Shaw
BLD-Foundation1/21/20201/22/20201/22/2020PPASS
DetailsBrandon Shaw
First floor slab and interior footings...
BLD-Footing12/3/201912/4/201912/4/2019APASS
DetailsBrandon Shaw
Mark Phone #: ###-####
BLD-Foundation11/1/201911/1/201911/1/2019PPASS
DetailsDave Hannah
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing10/30/201910/30/201910/30/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Foundation9/13/20199/16/20199/16/2019APASS
DetailsBrandon Shaw
Work in progress...
BLD-Foundation8/9/20198/12/20198/12/2019APART
DetailsBrandon Shaw
Back East wall only....
BLD-Footing8/1/20198/1/20198/1/2019PPASS
DetailsBrandon Shaw
Entire residence and pool footings...
Work in progress...
BLD-Footing7/25/20197/25/20197/25/2019PNR
DetailsBrandon Shaw
Need soil subgrade submitted and approved by PW...
BLD-Footing7/22/20197/23/20197/23/2019ANR
DetailsBrandon Shaw
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing7/19/20197/19/20197/19/2019PNR
DetailsJim Storey
Wes Phone #: ###-#### A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.