BLD-Final | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Tony Young
|
|
|
mark Phone #: ###-####
|
DOC - Permit Finaled | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/22/2020 | 4/22/2020 | 4/23/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/21/2020 | 4/21/2020 | 4/22/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Tony Young
|
|
|
Mark,, house ok to cover
|
BLD-Framing/Rough-in | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####,, ok to insulate
|
BLD-Wall Bracing | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####.. garage ok
|
BLD-Conference | 10/2/2019 | 10/3/2019 | 10/3/2019 | A | DEFR |
Brandon Shaw
|
|
|
Head room issue at, header to bottom tread, stairs to basement... Need Enggineering approval for for floor truss modification...
|
BLD-Wall Bracing | 9/20/2019 | 9/20/2019 | 9/20/2019 | P | PART |
Tony Young
|
|
|
Kai Phone #: ###-####,, house work in progress,, ok,, verify hold downs at the frame
|
BLD-Wall Bracing | 9/19/2019 | 9/19/2019 | 9/20/2019 | P | NR |
Dave Hannah
|
|
|
Marc Phone #: ###-#### needs 9 hold downds restaple and nial front wall
|
BLD-Foundation | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Tony Young
|
|
|
Adam-wll-pour time 1:30 Phone #: ###-####.. garage wall ok
|
BLD-Footing | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PART |
Tony Young
|
|
|
ADAM- concrete at 3pm Phone #: ###-####,, garage footings ok,, work in progress
|
BLD-Foundation | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | PART |
Mike Jordan
|
|
|
aDAM- CONRETE AT 2PM-FOUNDATION WALL Phone #: ###-####
|
BLD-Footing | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Tony Young
|
|
|
concrete at 2 // Adam Phone #: ###-####,, basement footings ok
|